3 Items Performance of an Asset is Based On ✔Correct Answer-1. Inherent Reliability
2. Operating Environment
3. Maintenance Plan
Benchmark - Maintenance Cost as % of RAV ✔Correct Answer-2% - 3%
Benchmark - Maintenance Cost as % of RAV ✔Correct Answer-0.25% - 1.25%
Benchmark - Schedule Compliance ✔Correct Answer->90%
Benchmark - Percent of Planned Work ✔Correct Answer->85%
Benchmark - Production/Operations Breakdown Losses ✔Correct Answer-1% - 2%
Benchmark - Parts Stock Out Rate ✔Correct Answer-1% - 2%
Leadership Attributes Survey ✔Correct Answer-Vision - 33%
Energizing People - 31%
Communication - 21%
Competence - 8%
Charisma - 7%
Mission Statement Benefits (3) ✔Correct Answer-1. Help companies focus their strategy by
defining boundaries within which to operate
2. Define dimensions along which an organization performance is measured and judged
3. Suggest standards for individual ethical behavior
2 Key Elements of Successful Effort to Change Culture ✔Correct Answer-1. Influencing behavior to
change
2. Overcoming resistance to change
Actions to Influence Change (6) ✔Correct Answer-1. Increase understanding
2. Set goals and expectations
3. Establish a process for praise and recognition
4. Define and clarify roles
5. Establish and standardize process and procedures
6. Create discipline, develop tenacity, and be persistent
Key Performance Indicators Attributes (3) ✔Correct Answer-1. Encourage the right behavior
2. Difficult to manipulate
3. Easy to measure
Condition Based Maintenance ✔Correct Answer-Vibration analysis
Infrared thermography
,Acoustic/ultrasonic
Oil analysis
Electrical
Shock pulse method
Partial discharge and corona discharge
Operational performance - pressure, temp, flow rates, etc.
3 Cautions with Preventive Maintenance ✔Correct Answer-1. Intrusive inspections
2. Tasks must be reviewed frequently to determine accuracy
3. Equip,met is hazarded and frequently degraded by tasks
Condition Based Maintenance Activities (3) ✔Correct Answer-1. Condition Measurement
2. Condition monitoring and health assessment
3. Repair and maintenance actions
Reliability Centered Maintenance ✔Correct Answer-A systematic, disciplined process to ensure
safety, mission compliance, and system function
Defines system boundaries and identifies system functions, functional failures, and likely failure
modes for equipment and structures in a specific operating context
4 Essential Elements of RCM ✔Correct Answer-1. Define system and required functions
2. Define functional failures and specific component failure modes that can defeat required functions
3. Prioritize the importance of the failure modes
4. Select the applicable and effective PM countermeasure for the high priority failure modes
Key Players in the Work Process ✔Correct Answer-Coordinator - asset/resource
Planner
Scheduler
Configuration specialist
Craft supervisor
Work performer
Benchmark - % of Planned Work ✔Correct Answer-> 90%
Benchmark - % of Schedule Compliance ✔Correct Answer-> 85%
Benchmark - % of Time the Right Part is Delivered ✔Correct Answer-> 99%
Economic Order Quantity ✔Correct Answer-
3 Key Parts of Asset Reliability ✔Correct Answer-Asset function
Conditions under which Asset operates
Mission time
Reliabiltiy ✔Correct Answer-Probability that an item will perform its intended function for a
specific interval under stated conditions
Availability ✔Correct Answer-Function of reliability and maintainability
Measured by degree to which an item or asset is an operable and committable state at the start of
the mission when the mission is called at an unspecified time
=MTBF/(MTBF+MTTR)
, Percentage of actual time that an asset is operated compared to how long it was scheduled to
operate
Cost Breakdown of Asset Life Cycle ✔Correct Answer-Design and development - 5-10%
Installation - 10 -20%
Operations and maintenance - 65 - 85%
Disposal - <5%
Key Elements of Reliability Specs ✔Correct Answer-Probability of successful performance
Function to be performed
Usage time
Operating conditions
Environment
Skill or operators/maintainers
Equipment Design Phase Analysis ✔Correct Answer-Reliability analysis
Maintain ability analysis
System safety and hazard analysis
Human factors engineering analysis
Logistics analysis
Total Productive Maintenance Pillars (8) ✔Correct Answer-1. Autonomous Maintenance
2. Focused Improvement
3. Planned maintenance
4. Quality maintenance
5. Training and development
6. Design and early equipment management
7. Office improvement
8. Safety, health, and environment
5S Steps ✔Correct Answer-Sort
Set in Order
Shine
Standardize
Sustain
(Safety)
Overall Equipment Effectiveness (OEE) ✔Correct Answer-Availability x Performance x Quality
Total Overall Equipment Effectiveness (TOEE) ✔Correct Answer-Utilization x availability x
performance x quality
Utilization ✔Correct Answer-Percentage of time equipment is used based on 24 hours per day and
365 days per year
Reliability Centered Maintenance Principles ✔Correct Answer-1. Primary objective is to preserve
system functions
2. Identify failure modes that can defeat the functions
3. Prioritize function needs
4. Select applicable and effective tasks
Professional Exam with All Correct & 100% Verified
Answers |Already Graded A+
3 Items Performance of an Asset is Based On ✔Correct Answer-1. Inherent Reliability
2. Operating Environment
3. Maintenance Plan
Benchmark - Maintenance Cost as % of RAV ✔Correct Answer-2% - 3%
Benchmark - Maintenance Cost as % of RAV ✔Correct Answer-0.25% - 1.25%
Benchmark - Schedule Compliance ✔Correct Answer->90%
Benchmark - Percent of Planned Work ✔Correct Answer->85%
Benchmark - Production/Operations Breakdown Losses ✔Correct Answer-1% - 2%
Benchmark - Parts Stock Out Rate ✔Correct Answer-1% - 2%
Leadership Attributes Survey ✔Correct Answer-Vision - 33%
Energizing People - 31%
Communication - 21%
Competence - 8%
Charisma - 7%
Mission Statement Benefits (3) ✔Correct Answer-1. Help companies focus their strategy by
defining boundaries within which to operate
2. Define dimensions along which an organization performance is measured and judged
3. Suggest standards for individual ethical behavior
2 Key Elements of Successful Effort to Change Culture ✔Correct Answer-1. Influencing behavior to
change
2. Overcoming resistance to change
Actions to Influence Change (6) ✔Correct Answer-1. Increase understanding
2. Set goals and expectations
3. Establish a process for praise and recognition
4. Define and clarify roles
5. Establish and standardize process and procedures
6. Create discipline, develop tenacity, and be persistent
Key Performance Indicators Attributes (3) ✔Correct Answer-1. Encourage the right behavior
2. Difficult to manipulate
3. Easy to measure
Condition Based Maintenance ✔Correct Answer-Vibration analysis
Infrared thermography
,Acoustic/ultrasonic
Oil analysis
Electrical
Shock pulse method
Partial discharge and corona discharge
Operational performance - pressure, temp, flow rates, etc.
3 Cautions with Preventive Maintenance ✔Correct Answer-1. Intrusive inspections
2. Tasks must be reviewed frequently to determine accuracy
3. Equip,met is hazarded and frequently degraded by tasks
Condition Based Maintenance Activities (3) ✔Correct Answer-1. Condition Measurement
2. Condition monitoring and health assessment
3. Repair and maintenance actions
Reliability Centered Maintenance ✔Correct Answer-A systematic, disciplined process to ensure
safety, mission compliance, and system function
Defines system boundaries and identifies system functions, functional failures, and likely failure
modes for equipment and structures in a specific operating context
4 Essential Elements of RCM ✔Correct Answer-1. Define system and required functions
2. Define functional failures and specific component failure modes that can defeat required functions
3. Prioritize the importance of the failure modes
4. Select the applicable and effective PM countermeasure for the high priority failure modes
Key Players in the Work Process ✔Correct Answer-Coordinator - asset/resource
Planner
Scheduler
Configuration specialist
Craft supervisor
Work performer
Benchmark - % of Planned Work ✔Correct Answer-> 90%
Benchmark - % of Schedule Compliance ✔Correct Answer-> 85%
Benchmark - % of Time the Right Part is Delivered ✔Correct Answer-> 99%
Economic Order Quantity ✔Correct Answer-
3 Key Parts of Asset Reliability ✔Correct Answer-Asset function
Conditions under which Asset operates
Mission time
Reliabiltiy ✔Correct Answer-Probability that an item will perform its intended function for a
specific interval under stated conditions
Availability ✔Correct Answer-Function of reliability and maintainability
Measured by degree to which an item or asset is an operable and committable state at the start of
the mission when the mission is called at an unspecified time
=MTBF/(MTBF+MTTR)
, Percentage of actual time that an asset is operated compared to how long it was scheduled to
operate
Cost Breakdown of Asset Life Cycle ✔Correct Answer-Design and development - 5-10%
Installation - 10 -20%
Operations and maintenance - 65 - 85%
Disposal - <5%
Key Elements of Reliability Specs ✔Correct Answer-Probability of successful performance
Function to be performed
Usage time
Operating conditions
Environment
Skill or operators/maintainers
Equipment Design Phase Analysis ✔Correct Answer-Reliability analysis
Maintain ability analysis
System safety and hazard analysis
Human factors engineering analysis
Logistics analysis
Total Productive Maintenance Pillars (8) ✔Correct Answer-1. Autonomous Maintenance
2. Focused Improvement
3. Planned maintenance
4. Quality maintenance
5. Training and development
6. Design and early equipment management
7. Office improvement
8. Safety, health, and environment
5S Steps ✔Correct Answer-Sort
Set in Order
Shine
Standardize
Sustain
(Safety)
Overall Equipment Effectiveness (OEE) ✔Correct Answer-Availability x Performance x Quality
Total Overall Equipment Effectiveness (TOEE) ✔Correct Answer-Utilization x availability x
performance x quality
Utilization ✔Correct Answer-Percentage of time equipment is used based on 24 hours per day and
365 days per year
Reliability Centered Maintenance Principles ✔Correct Answer-1. Primary objective is to preserve
system functions
2. Identify failure modes that can defeat the functions
3. Prioritize function needs
4. Select applicable and effective tasks