CCSM Exam
**Question 1. Which of the following is the primary purpose of a Job Hazard Analysis (JHA)?**
A) To estimate project cost
B) To identify potential safety hazards before work begins
C) To develop a marketing plan
D) To schedule material deliveries
Answer: B
Explanation: A JHA systematically reviews each step of a task to uncover hazards and determine
control measures, thereby preventing injuries.
**Question 2. Under OSHA 29 CFR 1926, which document must be kept on‑site for all
construction activities involving fall protection?**
A) Safety Data Sheet (SDS)
B) Fall Protection Plan (FPP)
C) Environmental Impact Report
D) Material Submittal Log
Answer: B
Explanation: The Fall Protection Plan outlines procedures, equipment, and training required to
protect workers from falls, and OSHA mandates its availability on site.
**Question 3. In a Critical Path Method (CPM) schedule, which activity determines the shortest
possible project duration?**
A) The activity with the highest float
B) The activity with the longest duration regardless of dependencies
C) The sequence of activities with zero total float
D) Any activity that is scheduled first
Answer: C
, AICM Certified Construction Site Manager
CCSM Exam
Explanation: The critical path consists of activities that have zero total float; any delay on these
activities directly extends the project duration.
**Question 4. Which of the following is NOT a typical component of an Inspection and Test Plan
(ITP) for structural concrete?**
A) Concrete mix design verification
B) Rebar placement inspection
C) Soil compaction testing for backfill
D) Final paint color approval
Answer: D
Explanation: Paint color approval pertains to finishes, not to structural concrete; the other items
directly relate to concrete quality.
**Question 5. When a subcontractor submits a Request for Information (RFI), the construction
manager should first:**
A) Issue a change order
B) Forward it to the client for approval
C) Review the drawing revision status and provide clarification
D) Reject it if it is not related to cost
Answer: C
Explanation: The manager verifies whether the question is already answered in existing
documents before escalating, ensuring efficient communication.
**Question 6. Which OSHA standard specifically addresses excavation and trench safety?**
A) 29 CFR 1926.500
B) 29 CFR 1926.650
C) 29 CFR 1926.700
, AICM Certified Construction Site Manager
CCSM Exam
D) 29 CFR 1926.850
Answer: B
Explanation: OSHA 29 CFR 1926.650 covers requirements for protective systems, soil
classification, and inspections for excavations.
**Question 7. In resource allocation, “just‑in‑time” delivery primarily aims to:**
A) Reduce labor overtime costs
B) Minimize on‑site material inventory and storage space
C) Increase the number of subcontractors on site
D) Extend the project schedule for better quality control
Answer: B
Explanation: Just‑in‑time delivery schedules materials to arrive when needed, reducing storage
requirements and potential waste.
**Question 8. Which of the following is a leading indicator of safety performance on a
construction site?**
A) Number of recordable injuries last year
B) Frequency of safety toolbox talks conducted weekly
C) Total compensation paid for workers’ compensation claims
D) Number of lost‑time accidents in the previous month
Answer: B
Explanation: Leading indicators, such as proactive safety activities, predict future performance,
whereas lagging indicators reflect past incidents.
**Question 9. A “fast‑track” construction schedule is best described as:**
A) Adding extra labor to accelerate all activities equally
, AICM Certified Construction Site Manager
CCSM Exam
B) Overlapping design and construction phases to reduce total duration
C) Using only prefabricated components to speed assembly
D) Extending work hours to 24‑hour shifts
Answer: B
Explanation: Fast‑tracking compresses the schedule by performing design and construction
activities in parallel, thereby shortening overall time.
**Question 10. When reviewing a subcontractor’s material submittal, the construction manager
should verify that the material meets which of the following?**
A) The subcontractor’s preferred brand
B) The project’s approved specifications and applicable ASTM/ISO standards
C) The lowest possible cost regardless of performance
D) The contractor’s internal inventory list
Answer: B
Explanation: Submittals must conform to the contract specifications and recognized standards
to ensure quality and compliance.
**Question 11. In the context of construction site health, which of the following is a required
element of an on‑site first‑aid station?**
A) A full‑time medical doctor on site
B) An AED (Automated External Defibrillator) if the site employs more than 50 workers
C) A stocked kit with bandages, splints, and emergency contact information
D) A dedicated ambulance service on standby at all times
Answer: C
Explanation: OSHA requires a readily accessible first‑aid kit with basic supplies; additional
equipment like AEDs is recommended but not always mandatory.