2) When the contractor is delinquent on contract performance, the two types of delinquency notices sent by the Contracting Officer are: [Discuss when and why schedule compliance must be brought to the attention of the KO] [Remediation Accessed
:N] A Cure Notice and a Show Cause Notice. The two notices may be used sequentially or, depending on the time left in performance, only a single notice might be used. A Second Chance Notice and a Show Cause Notice. The two notices may be used sequentially or, depending on the time left in performance, only a single notice might be used. A Cure Notice and a Termination Notice. The two notices may be used sequentially or, depending on the time left in performance, only a single notice might be used. A Termination for Default Notice and a Cure Notice. The two notices may be used sequentially or, depending on the time left in performance, only a single notice might be used. 3) You, as a COR, are giving technical direction to the contractor. This is adding value for the government and additional expense to the contractor. This is within the scope of the COR duties. [Distinguish between formal and informal communication and its effect on giving technical direction] True False