QUESTIONS AND SOLUTIONS RATED A+
✔✔According to PEI RP300, as-built drawings or photos of the underground piping and
other components should be maintained:
a. for at least 5 years
b. for at least 10 years
c. as long as the UST is in service
d. indefinitely - ✔✔c. as long as the UST is in service
✔✔According to Executive Order VR-101-E maintenance records are required to
include all of the following items EXCEPT the:
a. name of the designated UST operator
b. name of the individual making the repair
c. date the failure occurred or was observed
d. phone number of the individual making the repair - ✔✔a. name of the designated
UST operator
✔✔In a balance system, the vapor returns to the underground tank through all of the
following EXCEPT:
a. bellows
b. inner hose
c. breakaway valve
d. dispenser vapor piping - ✔✔b. inner hose
✔✔The Phil-Tite EVR Phase I system requires that vapor vent pipes at any UST system
be:
a. manifolded belowground
b. manifolded aboveground
c. manifolded to install one P/V valve
d. used with no more than 3 P/V valves - ✔✔d. used with no more than 3 P/V valves
✔✔After July 1, 2003, the definition of piping includes the following EXCEPT:
a. tank (fill) riser
b. product piping
c. dispenser hose
d. vapor recovery and vent piping - ✔✔c. dispenser hose
✔✔Under Dispenser Containment (UDC) is required to be designed and constructed in
accordance with:
, a. the appropriate executive order
b. generally accepted secondary containment practices
c. standards of an independent testing organization with industry code
d. an engineering specification approved by a state-registered professional engineer or
engineering standard - ✔✔c. standards of an independent testing organization with
industry code
✔✔Given: Oxygen depletion produces a range of physiological effects that worsen as
oxygen content is lowered or exposure time is increased.
The first sign of oxygen depletion is:
a. dizziness
b. rapid fatigue
c. labored breathing
d. accelerated respiration and heartbeat - ✔✔a. dizziness
✔✔Where a vapor shear valve is required, it is installed in the vapor piping at the:
a. vapor adaptor
b. entrance to a condensate tank
c. base of each dispensing device
d. extractor fitting or the ball float valve - ✔✔b. entrance to a condensate tank
✔✔A positive shutoff overfill prevention device (overfill valve) must stop the flow of fuel
when the fuel is more than ____ % of the tank capacity.
a. 85
b. 90
c. 95
d. 97 - ✔✔c. 95
✔✔Which of the following is not an overfill device?
a. ball float
b. spill bucket
c. tank overfill alarm
d. drop tube flapper valve - ✔✔b. spill bucket
✔✔According to CCR, Title 23, UST Regulations, a spill container must have a
minimum capacity of ____ gallons.
a. 5
b. 10