_____ ________ is a theory put forward by Lauri Koskela which
states that construction management involves the transformation
of inputs into outputs, a flow of material and information
through a production system, and management of the value most
important to the customers. Correct Answers TFV Theory
_______ ______________ aims to improve system performance
by reducing variation and then going for speed. Correct Answers
Lean Construction
__________ is the progression of work from production unit to
production unit, or within a production unit, and variation harms
the system performance by interrupting workflow. Correct
Answers Workflow
__________ workflow variation makes project outcomes
______ predictable. Correct Answers Reducing, more
___________ is the ability to deviate from standard procedures
in a creative but productive way Correct Answers Variability
_____________ _________ ______________ is an inherently
random source of variation that is property of the process or the
procedure. Correct Answers Common Course Variation
_____________ _________ ______________ is variation
caused by factors external to the defined process. Correct
Answers Special Cause Variation
, A random or non-random difference in a production process that
we can measure and quantify is ____________. Correct
Answers Variation
A set of ideas, practiced by individuals in the Construction
industry, based in the holistic pursuit of continuous
improvements aimed at minimizing costs and maximizing value
to clients in all dimensions of the built and natural environment:
planning, design, construction, activation, operations,
maintenance, salvaging, and recycling is ________
_________________. Correct Answers Lean Construction
All _______________ _________________ exhibit variation.
Correct Answers Production Processes
Any Process output outside the upper and lower control limits
indicates the presence of __________ _________ variation.
Correct Answers Special Cause
Any Variation within the upper and lower control limits is
__________ _________ variation. Correct Answers Common
Cause
Important Concept: What is a Buffer? Correct Answers A
mechanism to reduce the impact of variation on a construction
operation
Important Concept: What is Cycle Time? Correct Answers The
time it takes to complete one finished unit of a process
Solutions
_____ ________ is a theory put forward by Lauri Koskela which
states that construction management involves the transformation
of inputs into outputs, a flow of material and information
through a production system, and management of the value most
important to the customers. Correct Answers TFV Theory
_______ ______________ aims to improve system performance
by reducing variation and then going for speed. Correct Answers
Lean Construction
__________ is the progression of work from production unit to
production unit, or within a production unit, and variation harms
the system performance by interrupting workflow. Correct
Answers Workflow
__________ workflow variation makes project outcomes
______ predictable. Correct Answers Reducing, more
___________ is the ability to deviate from standard procedures
in a creative but productive way Correct Answers Variability
_____________ _________ ______________ is an inherently
random source of variation that is property of the process or the
procedure. Correct Answers Common Course Variation
_____________ _________ ______________ is variation
caused by factors external to the defined process. Correct
Answers Special Cause Variation
, A random or non-random difference in a production process that
we can measure and quantify is ____________. Correct
Answers Variation
A set of ideas, practiced by individuals in the Construction
industry, based in the holistic pursuit of continuous
improvements aimed at minimizing costs and maximizing value
to clients in all dimensions of the built and natural environment:
planning, design, construction, activation, operations,
maintenance, salvaging, and recycling is ________
_________________. Correct Answers Lean Construction
All _______________ _________________ exhibit variation.
Correct Answers Production Processes
Any Process output outside the upper and lower control limits
indicates the presence of __________ _________ variation.
Correct Answers Special Cause
Any Variation within the upper and lower control limits is
__________ _________ variation. Correct Answers Common
Cause
Important Concept: What is a Buffer? Correct Answers A
mechanism to reduce the impact of variation on a construction
operation
Important Concept: What is Cycle Time? Correct Answers The
time it takes to complete one finished unit of a process