CON 3900 Practice Exam Questions with Correct
Answers
Save
Terms in this set (150)
Market research is All phases of the acquisition
conducted during which
phase of acquisition?
What is the use of a Deviation
procedure that is
inconsistent with the FAR?
Simplified Acquisition Promote competition to the maximum extent
Procedures (SAP) should practicable
What is the tool (form) DD Form 1547, Weighted Guidelines Method
used by DoD to apply a
structured profit/fee?
What type(s) of contracts Only firm-fixed-price contracts or fixed-price
can be awarded when contracts with economic price adjustment
acquiring commercial
items of supply?
When using invitations for Only firm-fixed-price contracts or fixed-price
bids (IFBs), what type(s) of contracts with economic price adjustment
contracts can be
awarded?
,Which of the following is The DFARS PGI is a companion resource to the
correct regarding the DFARS
DFARS Procedures
Guidance and Information
(PGI)?
Which of the following Only contracting officers acting within the scope of
statements is accurate their authority are authorized to execute contract
regarding the modifications on behalf of the Government
Government's policy on
contract modifications?
Which of the following is Are only signed by a Government contracting officer,
accurate about unilateral not the contractor
modifications?
Except when authorized Must be in writing
otherwise, a Government
contract:
Which is NOT a type of Executive contracting officer
contracting officer?
With respect to the Ensure that each has been met
requirements of law,
executive orders,
regulations, and all other
applicable procedures,
prior to signing a contract,
a contracting officer must:
Joan stated that she was Has not been awarded
working on selecting
solicitation provisions.
With this in mind, you
know the contract:
, A program manager asked A contract clause is a term or condition used in
John whether a contract contracts, or in both solicitations and contracts, that
clause is only used in the applies after contract award or both before and after
contract or if it applies to award
the solicitation as well.
John correctly answered
by replying with which of
the following statements?
A contractor failed to Termination for Cause
deliver a commercial item
within the time specified
by the contract. As the
Government contracting
officer, you plan to
terminate the contract.
What type of termination
would you proceed with?
Which FAR part sets forth FAR part 1
the basic policies and
general information about
the Federal Acquisition
Regulations System?
Which of the following Each authority is delegable unless specifically stated
statements best conveys otherwise
the convention at FAR
1.108(b), delegation of
authority?
How many parts are there 53
in the FAR?
What is a Procurement A unique number identifying each solicitation,
Instrument Identifier contract, agreement, or order and related
(PIID)? procurement instrument
Answers
Save
Terms in this set (150)
Market research is All phases of the acquisition
conducted during which
phase of acquisition?
What is the use of a Deviation
procedure that is
inconsistent with the FAR?
Simplified Acquisition Promote competition to the maximum extent
Procedures (SAP) should practicable
What is the tool (form) DD Form 1547, Weighted Guidelines Method
used by DoD to apply a
structured profit/fee?
What type(s) of contracts Only firm-fixed-price contracts or fixed-price
can be awarded when contracts with economic price adjustment
acquiring commercial
items of supply?
When using invitations for Only firm-fixed-price contracts or fixed-price
bids (IFBs), what type(s) of contracts with economic price adjustment
contracts can be
awarded?
,Which of the following is The DFARS PGI is a companion resource to the
correct regarding the DFARS
DFARS Procedures
Guidance and Information
(PGI)?
Which of the following Only contracting officers acting within the scope of
statements is accurate their authority are authorized to execute contract
regarding the modifications on behalf of the Government
Government's policy on
contract modifications?
Which of the following is Are only signed by a Government contracting officer,
accurate about unilateral not the contractor
modifications?
Except when authorized Must be in writing
otherwise, a Government
contract:
Which is NOT a type of Executive contracting officer
contracting officer?
With respect to the Ensure that each has been met
requirements of law,
executive orders,
regulations, and all other
applicable procedures,
prior to signing a contract,
a contracting officer must:
Joan stated that she was Has not been awarded
working on selecting
solicitation provisions.
With this in mind, you
know the contract:
, A program manager asked A contract clause is a term or condition used in
John whether a contract contracts, or in both solicitations and contracts, that
clause is only used in the applies after contract award or both before and after
contract or if it applies to award
the solicitation as well.
John correctly answered
by replying with which of
the following statements?
A contractor failed to Termination for Cause
deliver a commercial item
within the time specified
by the contract. As the
Government contracting
officer, you plan to
terminate the contract.
What type of termination
would you proceed with?
Which FAR part sets forth FAR part 1
the basic policies and
general information about
the Federal Acquisition
Regulations System?
Which of the following Each authority is delegable unless specifically stated
statements best conveys otherwise
the convention at FAR
1.108(b), delegation of
authority?
How many parts are there 53
in the FAR?
What is a Procurement A unique number identifying each solicitation,
Instrument Identifier contract, agreement, or order and related
(PIID)? procurement instrument