Which of these is not a responsibility of the sender of the message?
Use words receiver can understand
Reduce distractions
Commit to the sender
Listen for feedback
Obtain commitment from receiver - Answer-Commit to the sender

______________ is an advantage of effective listening.
Building relationships
Building a good reputation
All of the listed advantages
Saving time
Increased productivity - Answer-All of the listed advantages


Compressing a project schedule requires
increasing the float for non-critical activities
making the critical path longer
decreasing the float for non-critical activities
making the critical path shorter - Answer-making the critical path shorter

The NIL, network interaction limit, must be smaller than the number of days to shorten
an activity on the critical path. - Answer-False

The activity that ___________ and least duration occurs when cost of the activity
graphed over time:
has the shortest duration
has the highest cost
has the longest duration
has the lowest cost - Answer-has the lowest cost


When a project is updated, the critical path may change either in route or length. -
Answer-True

An example of units completed measures is:

, A. CYDs excavated over total CYDs planned
B. Roof over foundation
C. Inches over foot
D. Feet over mile - Answer-A. CYDs excavated over total CYDs planned

Project controls include each of these except:
A. Time or cost ratio
B. Superintendent opinion
C. Incremental milestones
D. Owner's opinion - Answer-D. Owner's opinion

An engineering design firm does not need to know how to control a project (the develop
of the design of a building or highway). - Answer-False

Supervisor's opinion of percent complete is a ______________ measure.
A. Objective
B. Subjective
C. Successive
D. Iterative - Answer-B. Subjective

If a pipe installation activity takes one week to complete 1,000 linear feet, the
productivity of the activity is:
A. 5,000 linear feet per week
B. 200 linear feet per day
C. 400 linear feet per hour
D. 500 linear feet per day - Answer-B. 200 linear feet per day

Predecessor and successor activities on a linear schedule can (choose all valid
answers)
A. Finish at the same time
B. Have a minimum buffer between them
C. Cross so the successor becomes a predecessor
D. Start at the same time - Answer-A. Finish at the same time
B. Have a minimum buffer between them
D. Start at the same time
(This is the same as a finish-finish relationship

A buffer can be based on time or distance.

This is the same as a start-start network relationship)

An activity in a linear schedule usually is represented by a line which shows
A. The ratio of workers to supervisors on the activity
B. The rate of expenditures on the project, usually dollars per day
C. The direction of the activity, usually north, south, east, or west

Document information

Uploaded on
December 3, 2025
Number of pages
9
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$14.59

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Perfectscorer
3.6
(75)
Sold
501
Followers
355
Items
9427
Last sold
2 weeks ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions