Answers
True or false: Product design is integral to the success of many
businesses. - 🧠 ANSWER ✔✔True
Place the following steps in the generic product development process in the
correct sequence.
Planning
Production ramp-up
Concept development
Testing and refinement
Detail design
,System-level design - 🧠 ANSWER ✔✔Planning
Concept-development
System-level design
Detail design
Testing and refinement
Production ramp-up
True or false: The planning phase precedes the project approval. - 🧠
ANSWER ✔✔True
In what phase are the needs of the target market identified? - 🧠 ANSWER
✔✔Concept
True or false: The final assembly scheme for the production scheme is
usually defined in the system-level design phase.
True false question. - 🧠 ANSWER ✔✔True
Which of the following is not included in the detail design phase of the
product development process?
A. Business goals
, B. Standard parts
C. Tooling
D. Process plan - 🧠 ANSWER ✔✔A. Business goals
What are the outputs of the detail design phase. Check all that apply.
A. A preliminary process flow diagram for the final assembly process
B. The process plans for the fabrication and assembly of the product
C. A decision regarding which outsourcing company to use for each part
D. The specifications of purchased parts
E. Drawings or computer files describing the geometry of each part
F. A geometric layout of the product - 🧠 ANSWER ✔✔B. The process plans
for the fabrication and assembly of the product
D. The specifications of purchased parts
E. Drawings or computer files describing the geometry of each part
Which of the following can be used to construct a base-case model for a
new-product development project?
A. QFD