1. Which of the following best defines cost estimating?
A. Developing a detailed project schedule
B. Predicting future costs based on data and experience
C. Allocating project funds across departments
D. Determining the financial feasibility of a project
Answer: B
Cost estimating involves forecasting future costs using data, experience, and
judgment.
2. A bottom-up estimate is most appropriately used when:
A. The project scope is undefined
B. Historical data is unavailable
C. Detailed design information is available
D. Parametric models are required
Answer: C
Bottom-up estimating relies on detailed component-level information.
3. Which cost classification includes expenses that vary with output?
A. Fixed costs
B. Overhead costs
C. Variable costs
D. sunk costs
Answer: C
Variable costs rise or fall based on production levels.
4. The purpose of a Work Breakdown Structure (WBS) in estimating is to:
A. Determine schedule activities
B. Break the project into manageable cost components
C. Allocate resources
,D. Ensure stakeholder communication
Answer: B
A WBS organizes project scope into cost-estimating elements.
5. The accuracy range of a Class 5 estimate typically is:
A. −10% to +10%
B. −15% to +20%
C. −20% to +30%
D. −50% to +100%
Answer: D
Class 5 estimates are conceptual with very limited definition.
6. Regression analysis is used in cost estimating primarily for:
A. Expert judgment
B. Parametric modeling
C. Cost classification
D. Cash-flow forecasting
Answer: B
Regression forms the mathematical basis of many parametric models.
7. A contingency reserve is used to cover:
A. Major scope changes
B. Unknown-unknowns
C. Known-unknowns
D. Escalation costs
Answer: C
Contingency addresses identified risks with uncertain impacts.
8. Which of the following is NOT a cost estimating input?
A. Scope documents
B. Cost databases
C. Risk register
, D. Earned value results
Answer: D
EVM results are used for performance monitoring, not early estimates.
9. Learning curves predict that:
A. Costs increase with experience
B. Labor hours decrease with repetition
C. Materials become more expensive over time
D. Productivity is constant
Answer: B
Learning curves show improved efficiency with repetition.
10. What is the primary purpose of escalation in an estimate?
A. Cover project risks
B. Account for price growth over time
C. Address schedule delays
D. Adjust for overhead costs
Answer: B
Escalation reflects expected inflation or price growth.
11. The cost baseline includes:
A. Estimate + contingency
B. Estimate + reserves
C. Estimate + contingency + management reserve
D. Direct costs only
Answer: A
The cost baseline equals the estimate plus contingency (but not MR).
12. The best estimating method for a repetitive manufacturing environment
is:
A. Bottom-up
B. Analogous