During the construction of a recent office building, your company’s framing
crew installed 515 lineal feet of 8-foot-high, metal-stud wall in two days. The
crew consisted of two carpenters and one helper and worked eight hours
per day. Determine productivity rate in labor hours per foot of wall for
installing metal-stud walls on this project.
Question 1Select one:
a.
0.093 lhr/lft
b.
0.084 lhr/lft
c.
, 0.102 lhr/lft
100.00 out of 100.00) NEW UPDATE 2025-2026 Louisiana
State University
Module 2 Quiz
Status Finished
Started Sunday, November 2, 2025, 12:06 PM
Completed Sunday, November 2, 2025, 12:09 PM
Duration 3 mins 38 secs
Points 20.00/20.00
Grade 100.00 out of 100.00
Question 1
Correct4.00 points out of 4.00Flag question
Question text
During the construction of a recent office building, your company’s framing
crew installed 515 lineal feet of 8-foot-high, metal-stud wall in two days. The
crew consisted of two carpenters and one helper and worked eight hours
per day. Determine productivity rate in labor hours per foot of wall for
installing metal-stud walls on this project.
Question 1Select one:
a.
0.093 lhr/lft
b.
0.084 lhr/lft
c.
, 0.102 lhr/lft