**Question 1.** Which delivery method combines design and construction
responsibilities under a single contract?
A) Design‑Bid‑Build
B) Construction‑Management‑At‑Risk
C) Design‑Build
D) Integrated Project Delivery
**Answer:** C
**Explanation:** In Design‑Build, a single entity is responsible for both design and
construction, streamlining communication and often reducing schedule risk.
**Question 2.** In CPM scheduling, which activity determines the project’s
minimum completion time?
A) Critical activity
B) Non‑critical activity
C) Float activity
D) Lag activity
**Answer:** A
**Explanation:** Critical activities have zero float; any delay directly extends the
project’s overall duration.
**Question 3.** Which plot is most suitable for visualizing the sequence and
duration of construction activities?
A) Histogram
, New York NY Engineering Exam
B) Gantt chart
C) Pareto chart
D) Scatter plot
**Answer:** B
**Explanation:** A Gantt chart displays tasks along a time axis, showing
start/finish dates and overlapping activities.
**Question 4.** When preparing a stormwater pollution prevention plan
(SWPPP), which control measure is primarily used to filter suspended solids?
A) Detention basin
B) Oil‑water separator
C) Sediment fence
D) Infiltration trench
**Answer:** C
**Explanation:** Sediment fences capture eroded soil particles, preventing them
from entering storm drains.
**Question 5.** In quantity take‑offs, the term “unit cost” refers to:
A) Cost per hour of labor
B) Cost per cubic yard of concrete
C) Total project cost
D) Overhead allocation rate
, New York NY Engineering Exam
**Answer:** B
**Explanation:** Unit cost is the price associated with a single unit of a material
or work item, such as $/yd³ of concrete.
**Question 6.** Which of the following is a primary ethical duty of a licensed
professional engineer in New York?
A) Maximizing profit for the client
B) Protecting the public health, safety, and welfare
C) Avoiding all communication with contractors
D) Delegating all design decisions to junior staff
**Answer:** B
**Explanation:** The code of ethics requires engineers to prioritize public safety
above all other considerations.
**Question 7.** The present worth factor for a uniform series of cash flows over n
periods at an interest rate i is:
A) (1‑(1+i)⁻ⁿ)/i
B) (1+i)ⁿ‑1/i
C) (1+i)⁻ⁿ
D) i/(1‑(1+i)⁻ⁿ)
**Answer:** A
**Explanation:** This factor converts a series of equal annual amounts to a single
present‑value amount.
, New York NY Engineering Exam
**Question 8.** OSHA requires a confined‑space entry permit to be signed by:
A) Only the entry supervisor
B) The entrant only
C) Both the entrant and the entry supervisor
D) The site owner only
**Answer:** C
**Explanation:** Both the entrant and the supervisor must sign to confirm that
safety procedures have been met.
**Question 9.** The Atterberg limit that indicates the water content at which a
fine‑grained soil changes from a plastic to a liquid state is:
A) Liquid limit
B) Plastic limit
C) Shrinkage limit
D) Plasticity index
**Answer:** A
**Explanation:** The liquid limit marks the transition from plastic to liquid
behavior.
**Question 10.** In the Unified Soil Classification System (USCS), a soil classified
as “SW‑C” has which dominant characteristics?