Exam Questions and Verified Answers |
Already Graded A+
When requirements necessary for proper operation of a proposed
mechanical system are not specifically covered by the code, such
requirements shall be determined by____________________. - 🧠ANSWER
✔✔The code official
Where the code official finds that a proposed alternative material does not
comply with the intent of the code provisions, the code official shall
_________________. - 🧠ANSWER ✔✔State the reason for disapproval in
writing to the applicant
The code official has the authority to______________the provisions of the
code. - 🧠ANSWER ✔✔Interpret
, One set of construction documents shall be kept_______________until
completion of the project. - 🧠ANSWER ✔✔At the job site
The______________shall be responsible for the scheduling of inspections.
- 🧠ANSWER ✔✔Holder of the permit
Which of the following installations is permitted to be backfilled prior to an
underground inspection? - 🧠ANSWER ✔✔Ground source heat pump loop
systems
Mechanical systems shall be tested, with such test made by the permit
holder and observed by the________________. - 🧠ANSWER ✔✔Code
official
A permit is not required for a self-contained refrigeration system that
contains a maximum of_______________pound(s) of refrigerant. -
🧠ANSWER ✔✔10
Heating, Ventilating and air-conditioning systems shall be designed and
installed for efficient use of energy in accordance with
the________________. - 🧠ANSWER ✔✔International energy conservation
code