VA DEQ ESC INSPECTOR EXAM (ALREADY) PASSED!!




VESCP Answer - Virginia Erosion and Sediment Control Program


- Administered by counties/cities (must), towns (may)
- MUST BE APPROVED


Minimum Standard 1 Answer - Stabilization


permanent or temporary soil stabilization shall be applied to denuded areas
within seven days after final grade is reached on any portion of the site;
temporary soil stabilization shall be applied within seven days to denuded
areas that may not be at final grade but will remain dormant for longer than 14
days; permanent stabilization shall be applied to areas that are to be left
dormant for more than one year


Site NOT at Final Grade Answer - - stabilize in 14 days
- temporarily seed
- mulch
- permanently stabilize if dormant > 1 year


Site at Final Grade Answer - - stabilize in 7 days (recommended immediately)
- permanently or temporarily seed and mulch
- mulch/matting/straw

,Minimum Standard 2 Answer - Stock Piles, Waste and Borrow Areas


during construction, soil stock piles and borrow areas shall be stabilized or
protected with sediment trapping measures


mulch prevents erosion by protecting the surface from raindrop impact and silt
fence intercepts and detains from disturbed areas


Minimum Standard 3 Answer - Permanent Vegetation


permanent vegetation cover shall be established on denuded areas not
otherwise permanently stabilized (permanent vegetation shall not be
considered established until a ground cover is achieved that is uniform, mature
enough to survive, and will inhibit erosion *there is no % associated with this*)


reduce erosion and decrease sediment yield from disturbed area


this is the standard used to verify that a site is ready for release of bonds or
surety


Minimum Standard 4 Answer - First-Step Measures


Sediment basins and traps, perimeter dikes, sediment barriers and other
measures intended to trap sediment shall be constructed as a first step in any
land-disturbing activity and shall be made functional before upslope land
disturbance takes place

,a certain amount of initial land disturbance may be required to provide access
for equipment to install the perimeter controls, but site clearing and grading
should be kept to a minimum until the perimeter controls are in place


intercepts and detains small amounts of sediment from disturbed areas during
construction operation to prevent sediment from leaving the site and decrease
velocity of sheet flows and low-to-moderate level channel flow


Perimeter Controls Answer - assures that sediment does not leave the
perimeter of the land-disturbing area once site clearing, grading, and
construction commences


Examples: silt fences, sediment traps, sediment basins, construction entrance,
temporary diversions, diversions


Minimum Standard 5 Answer - Earthen Structure Stabilization


stabilization measures shall be applied to earthen structures such as dams,
dikes, and diversions immediately after installation


reduce erosion and sedimentation and reduce damage from sediment and
runoff to downstream or off-site areas


Minimum Standard 6 Answer - Traps and Basins


sediment traps and basins shall be designed and constructed based upon the
total drainage area (not just disturbed area) to be served by the trap or basin


Sediment Traps Answer - minimum storage capacity shall be 134 cubic yards
per acre of drainage area and shall only control drainage areas less than 3 acres

, *stone outlet = trap*


Sediment Basins Answer - surface runoff from disturbed areas that is
comprised of flow from drainage areas greater than or equal to 3 acres shall be
controlled by a basin; minimum storage capacity of a sediment basin shall be
134 cubic yards per acre of drainage area; the outfall system shall, at a
minimum, maintain the structural integrity of the basin during a 25-year storm
of 24-hour duration; runoff coefficients used in runoff calculations shall
correspond to a bare earth condition or those conditions expected to exist
while the sediment basin is utilized.


Sediment Trapping Devises Answer - 1. place near the lowest drainage points
of a project


2. install as a first-step measure [MS-4]


3. stabilize immediately [MS-5]


4. must include outlet protection for basins [MS-11]


Minimum Standard 7 Answer - Cut and Fill Slopes


roughening the surface of the slope decreases runoff, lowers the velocity
runoff, increases water retention, and leads to better seed germination


slopes that are found to be eroding excessively within on year of permanent
stabilization shall be provided with additional slop stabilizing measures until
the problem is corrected

Document information

Uploaded on
November 19, 2025
Number of pages
35
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$24.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
EvaTee
3.9
(985)
Sold
5416
Followers
3581
Items
58842
Last sold
12 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions