VA DEQ ESC Inspector Exam


VESCP - AnswerVirginia Erosion and Sediment Control Program



- Administered by counties/cities (must), towns (may)

- MUST BE APPROVED



Minimum Standard 1 - AnswerStabilization



permanent or temporary soil stabilization shall be applied to denuded areas within seven
days after final grade is reached on any portion of the site; temporary soil stabilization shall
be applied within seven days to denuded areas that may not be at final grade but will remain
dormant for longer than 14 days; permanent stabilization shall be applied to areas that are
to be left dormant for more than one year



Site NOT at Final Grade - Answer- stabilize in 14 days

- temporarily seed

- mulch

- permanently stabilize if dormant > 1 year



Site at Final Grade - Answer- stabilize in 7 days (recommended immediately)

- permanently or temporarily seed and mulch

- mulch/matting/straw



Minimum Standard 2 - AnswerStock Piles, Waste and Borrow Areas

,during construction, soil stock piles and borrow areas shall be stabilized or protected with
sediment trapping measures



mulch prevents erosion by protecting the surface from raindrop impact and silt fence
intercepts and detains from disturbed areas



Minimum Standard 3 - AnswerPermanent Vegetation



permanent vegetation cover shall be established on denuded areas not otherwise
permanently stabilized (permanent vegetation shall not be considered established until a
ground cover is achieved that is uniform, mature enough to survive, and will inhibit erosion
*there is no % associated with this*)



reduce erosion and decrease sediment yield from disturbed area



this is the standard used to verify that a site is ready for release of bonds or surety



Minimum Standard 4 - AnswerFirst-Step Measures



Sediment basins and traps, perimeter dikes, sediment barriers and other measures intended
to trap sediment shall be constructed as a first step in any land-disturbing activity and shall
be made functional before upslope land disturbance takes place



a certain amount of initial land disturbance may be required to provide access for
equipment to install the perimeter controls, but site clearing and grading should be kept to a
minimum until the perimeter controls are in place



intercepts and detains small amounts of sediment from disturbed areas during construction
operation to prevent sediment from leaving the site and decrease velocity of sheet flows and
low-to-moderate level channel flow

,Perimeter Controls - Answerassures that sediment does not leave the perimeter of the land-
disturbing area once site clearing, grading, and construction commences



Examples: silt fences, sediment traps, sediment basins, construction entrance, temporary
diversions, diversions



Minimum Standard 5 - AnswerEarthen Structure Stabilization



stabilization measures shall be applied to earthen structures such as dams, dikes, and
diversions immediately after installation



reduce erosion and sedimentation and reduce damage from sediment and runoff to
downstream or off-site areas



Minimum Standard 6 - AnswerTraps and Basins



sediment traps and basins shall be designed and constructed based upon the total drainage
area (not just disturbed area) to be served by the trap or basin



Sediment Traps - Answerminimum storage capacity shall be 134 cubic yards per acre of
drainage area and shall only control drainage areas less than 3 acres



*stone outlet = trap*



Sediment Basins - Answersurface runoff from disturbed areas that is comprised of flow from
drainage areas greater than or equal to 3 acres shall be controlled by a basin; minimum
storage capacity of a sediment basin shall be 134 cubic yards per acre of drainage area; the
outfall system shall, at a minimum, maintain the structural integrity of the basin during a 25-
year storm of 24-hour duration; runoff coefficients used in runoff calculations shall
correspond to a bare earth condition or those conditions expected to exist while the
sediment basin is utilized.

, Sediment Trapping Devises - Answer1. place near the lowest drainage points of a
project



2. install as a first-step measure [MS-4]



3. stabilize immediately [MS-5]



4. must include outlet protection for basins [MS-11]



Minimum Standard 7 - AnswerCut and Fill Slopes



roughening the surface of the slope decreases runoff, lowers the velocity runoff,
increases water retention, and leads to better seed germination



slopes that are found to be eroding excessively within on year of permanent
stabilization shall be provided with additional slop stabilizing measures until the problem
is corrected



Minimum Standard 8 - AnswerConcentrated Runoff



shall not flow down cut or fill slopes unless contained within an adequate temporary or
permanent channel, flume or slope drain structure



outlets of these drains need outlet protection to prevent erosion from the concentrated
flow



size of pipe depends on drainage area

Document information

Uploaded on
November 16, 2025
Number of pages
31
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$18.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
0
Followers
0
Items
77
Last sold
-


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions