2026 COMPREHENSIVE QUESTIONS AND
ANSWERS
◉ The number of employees that will require a contractor to obtain
workman's compensation insurance is _____ or more full or part time
employee(s).
A. One
B. Three
C. Four
D. Ten. Answer: A. One
◉ The type of bond that guarantees that the contractor will perform
the work in accordance with the contract is known as a _____ Bond
A. Bid
B. Payment
C. Performance
D. Stipulated. Answer: C. Performance
◉ Of the following, which one is not included in the scope of a
certified alarm system contractor?
A. Alarm circuits not originating in the alarm panel
, B. Wiring for data transmission circuits that do not exceed 98 volts
(RMS)
C. Satellite systems that are not a part of a community antenna
television distribution system.
D. Fire Alarm systems. Answer: A. Alarm circuits not originating in
the alarm panel
◉ The ____ usually prepares the project schedule.
A. Architect
B. Owner
C. Project Manager
D. Engineer. Answer: C. Project Manager
◉ Employee Linda was paid a gross total wage of $63,500 last year.
The total amount withheld from her pay for Medicare and Social
Security was ____.
A. $4,295
B. $4,403
C. $4,858
D. $5,002. Answer: C. $4,858
◉ A contract will not be enforced if it is ___.
A. Oral