1|Page


CON 3990V Final Exam 2025 — DAU Contracting
Capstone, Practice Questions & Study Guide



Prepare for the CON 3990V Final Exam 2025 with a complete Defense Acquisition University
(DAU) study guide, practice tests, and key contracting principles. Review essential topics in
acquisition planning, cost analysis, source selection, and contract management to excel in
your DAU Capstone assessment.




• CON 3990V Final Exam 2025
• DAU CON 3990V study guide
• Contracting Capstone exam questions
• DAU contracting certification final exam




At what dollar value must a contracting officer synopsize a proposed contract action in the
Governmentwide point of entry (GPE)?(A. Expected to exceed $25,000)

B. Expected to be between $15,000 and $25,000

C. Only if exceeding $500,000

D. Only if exceeding $1,000,000



After release of the solicitation, who must be the focal point of any exchange with potential offerors?A.
The program manager

B. The technical lead

C. The cost/price analyst

(D. The contracting officer)



An overarching principle for responding to questions from all potential offerors is:(A. Fairness)

,2|Page


B. Brevity

C. Protest avoidance

D. Narrowing of competition



Whenever a contracting officer is required to publicize notice of proposed contract actions in the
Governmentwide point of entry (GPE), they must:A. Allow a different response time for each potential
offeror in order to promote better competition

(B. Establish a common response time for all offerors from the date of publication)

C. Include the independent Government estimate for the requirement

D. Include the most current budget for the resulting contract



Agencies shall conduct market research:A. In the same manner for all acquisitions for consistency
purposes

B. Only if unsure of adequate competition

(C. Appropriate to the circumstances)

D. Until release of the solicitation



To the maximum extent practicable, acquisition officials shall state requirements of supplies or services
in terms of functions to be performed, performance required, or:(A. Essential physical characteristics)

B. Commerciality

C. Requiring activity preference

D. Availability



When using FAR part 12 procedures, the technical evaluation would normally include examination of
such things as product literature, product samples (if requested), technical features, and:A. Management
plans

B. Manufacturing plans

C. Quality assurance plans

(D. Warranty provisions)

,3|Page


Provisions and clauses should be incorporated by reference in solicitations and contracts:A. Unless they
are used with more than one alternate, then full text is required

(B. Unless they are used with more than one alternate, then full text is required)

C. Unless they contain a blank within the text that the contracting officer must fill in prior to award

D. Unless the uniform contract format (UCF) applies



Which offerors receive an amendment on a solicitation that has yet to close?A. All parties in the
competitive range

B. None. Solicitations are modified, not amended.

(C. All parties receiving the solicitation)

D. None. Solicitations can't be amended until they have closed.



The purpose of exchanging information with industry before receipt of proposals is to:A. Always obtain
the lowest price for Government requirements

B. Find a sole source contractor to meet the Government's requirements

C. Negotiate the best deal in response to the Government's requirements

(D. Improve the understanding of Government requirements and industry capabilities)



Which of the following is the correct title of a solicitation for negotiated procedures?A. Invitation for
Proposals

(B. Request for Proposals)

C. Request for Cost Proposals

D. Invitation for Pricing




One day after publicizing and releasing a solicitation, the contracting officer realizes that the contract line
items need to be reorganized. The contracting officer must:A. Leave the solicitation as is and plan to
modify the contract after award

B. Wait to see if offerors have issues with the current contract line-item structure

(C. Amend the solicitation, changing the contract line item)

D. Publicize an advisory letter with the new contract line-item structure

, 4|Page




Which FAR part is the best source of information regarding competition requirements?A. FAR part 1

(B. FAR part 6)

C. FAR part 7

D. FAR part 13



You have determined that FAR part 12 applies to your commercial item requirement. Which of the
following contract types is appropriate when using FAR part 12 procedures?A. Fixed-price incentive

B. Firm-fixed price, level-of-effort

(C. Firm-fixed-price)

D. Cost-plus-fixed-fee



You are a DoD contracting officer and have used simplified acquisition procedures under FAR part 13 to
award a commercial purchase order for supplies. Given only this information, which form is most
appropriate to use should you need to modify your purchase order?(A. Standard Form 30, Amendment
of Solicitation/Modification of Contract)

B. Standard Form 1449, Solicitation/Contract/Order for Commercial Items

C. Standard Form 33, Solicitation, Offer and Award

D. DD Form 1155, Order for Supplies or Services



You're administering a large dollar non-commercial weapons contract. The contracting officer asks to see
the Contract Data Requirements List (CDRL) in Exhibit B. Which uniform contract format (UCF) section in
your contract would you refer to?A. Section A

B. Section C

C. Section I

(D. Section J)



Which of the following is specifically set up to help firms view current Government business
opportunities?(A. The Governmentwide Point of Entry (GPE))

B. The local office of the Small Business Administration (SBA)

C. The Chamber of Commerce

Document information

Uploaded on
November 6, 2025
Number of pages
32
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$24.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
profangel
4.8
(961)
Sold
35
Followers
33
Items
155
Last sold
1 year ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions