This document contains 185 exam questions with verified correct answers based on the MCPPO Design and Construction 2025/2026 curriculum, specifically focused on Massachusetts public construction law, contract compliance, and project administration. It is a complete and updated resource for candidates preparing for the MCPPO certification under the Office of the Inspector General of Massachusetts. Topics comprehensively covered include: The three phases of public construction: planning, design, and construction Responsibilities of the Owner’s Project Manager (OPM) and public awarding authorities Scope development, schematic design, construction documents, and designer selection Massachusetts General Laws (Ch. 30, 39M; Ch. 149; Ch. 7C), including requirements for bid deposits, payment bonds, and prevailing wage compliance Contract types, statutory provisions (Sections 39I, 39N, 39O, 39P), and dispute resolution including change orders, claims, and delays Procedures for public works and building projects exceeding $50,000 or $150,000 Record-keeping, performance evaluations, milestones, and deliverables This document is ideal for: Graduate and professional students in Construction Management, Public Administration, Civil Engineering, or Legal Studies Procurement officers, municipal project managers, engineers, or public-sector contractors preparing for MCPPO certification University and continuing education programs focused on public contracting or government infrastructure It serves both as a study aid and a practical reference for anyone involved in design and construction contracting for public projects in Massachusetts, ensuring complete alignment with current legislation and procurement standards. Keywords: MCPPO, design and construction, Massachusetts public procurement, Chapter 30, Chapter 149, Chapter 39M, public construction law, bid compliance, contract administration, owner’s project manager, schematic design, construction documents, contract law, public works, payment bond, prevailing wage, public bidding, change order, delay claims, false claims, dispute resolution

Content preview

MCPPO Design and Construction
2025/2026 Exam Questions with 100%
Correct Answers | Latest Update



What are the three stages of the design and construction process for public

construction projects in MA - 🧠 ANSWER ✔✔Planning, Design, and

Construction


What does the design stage result in? - 🧠 ANSWER ✔✔A complete set of

plans and specifications describing the project to be built.

What happens after a set of plans and specifications is complete? - 🧠

ANSWER ✔✔Bids are solicited on the completed design, and the selected

contractor completes the construction stage.

Who is always responsible and accountable for the project? - 🧠 ANSWER

✔✔Public Owner (Awarding Authority)

,Before contracting for design services in connection with a public building

contract estimated to cost $1.5 million or more, your jurisdiction is required

to do what? - 🧠 ANSWER ✔✔Contract with or assign an Owner's Project

Manager (OPM)

Serves as your jurisdiction's agent during the planning, design, and

implementation of the construction work. - 🧠 ANSWER ✔✔OPM


Independent of the project designer, general contractor, or any

subcontractor. - 🧠 ANSWER ✔✔OPM


I you elect to contract for the services of an OPM, what are you required to

do? - 🧠 ANSWER ✔✔Use a qualifications-based selection process, which

means that the OPM must be competitively selected on the basis of

qualifications, without price competition.


Can you assign an employee to serve as OPM? - 🧠 ANSWER ✔✔Yes, if

the employee meets or exceeds the requirements and has building

construction and supervision experience relating to projects of similar size

and scope of complexity.


What is a study? - 🧠 ANSWER ✔✔A pre-design document that:

,-Confirms and explains the owner's requirements

-Identifies and evaluates alternative solutions

-Recommends and defines a solution

Purpose is to identify the owner's needs and determine the most

appropriate and cost effective solution to meeting the needs. - 🧠 ANSWER

✔✔Study


True or False: A study may not result in a construction project. - 🧠

ANSWER ✔✔True


More refined and detailed than the conceptual drawings that were included

in the study. Includes floor plans, side views, and other illustrations. - 🧠

ANSWER ✔✔Schematic drawings


At the end of this phase, the designer should prepare and submit to the

owner a revised construction cost estimate. - 🧠 ANSWER ✔✔Schematic

Design Phase

Consists of plans and specifications that are between 10 percent and 30

percent complete. Presented to the owner as a deliverable. - 🧠 ANSWER

✔✔Schematic Design



COPYRIGHT©PROFFKERRYMARTIN 2025/2026. YEAR PUBLISHED 2025. COMPANY REGISTRATION NUMBER: 619652435. TERMS OF USE.
PRIVACY STATEMENT. ALL RIGHTS RESERVED

, Once the owner approves the schematic design documents, the project

may proceed to this phase.... - 🧠 ANSWER ✔✔Design Development


In this phase, the designer further refines the drawings and written

specifications by filling in construction details and incorporating changes in

response to the owner's review of the schematic design as well as changes

required by a regulatory agency. - 🧠 ANSWER ✔✔Design Development


In this phase, the design will be completed by filling in the final details - 🧠

ANSWER ✔✔Construction Documents


The deliverable of this design phase will be the 100 percent complete

design documents that will form the legal basis of the construction contract.

- 🧠 ANSWER ✔✔Construction Documents


Must be written to provide for full competition for each item of material to be

furnished under the contract - 🧠 ANSWER ✔✔Material Specifications


Specifications that restrict competition to fewer than three manufacturers or

producers may be used only for__________________________________

- 🧠 ANSWER ✔✔"Sound Reasons in the Public Interest"

Document information

Uploaded on
November 5, 2025
Number of pages
35
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$15.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
PROFFKERRYMARTIN
3.3
(63)
Sold
309
Followers
9
Items
11506
Last sold
2 hours ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions