The owner requests changes which will cost the contractor $2,500 in labor and materials and $700 in overhead costs. With the change, the contractor would be relieved of $1,000 in labor costs and $280 in overhead costs from the original contract. The original bid included profit of 10% of all costs. The contractor wants to make a profit of 10% of all costs on the changes. The amount of the change order should included a request of an additional. A. $1820 B. $2,112 C. $3,200 D. $3,520 - correct answer B. $2,112 A lump sum contract on a project has a total contract price of $200,000. Retainage has been held back at 10%. The contractor has received progress payments of 90% of the project. The contractor submits a request for the final payment for the now completed project. The final payment amount should be for A. less than 25,000$ b. between 25,000$ & 35,000$ c. between 35,000$ & 40,000$ d. more than 40,000$ - correct answer c. between 35,000$ & 40,000$ A contractor agrees to unit price contract to Product A fir $50 per unit, product B for $50 per unit, and product C for $375 per unit. The contractor is also to add 30% for overhead and profit. How much the contractor should be paid for producing 27 units of product A, 56 units of product B and 78 units of product C? a. less than 40,000$ b. between 40,000$ & 45,000$ c. between 45,000 & 50,000$ d. more than 50,000$ - correct answer b. between 40,000$ & 45,000$ A contract calls for liquidated damage of 500$ per day. The project completed five days late because it was delayed by rain. The completion would have been 10 days earlier if it were not for the rain

Mostrar más Leer menos
Institución
Virginia Contractors License
Grado
Virginia contractors license









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
Virginia contractors license
Grado
Virginia contractors license

Información del documento

Subido en
4 de noviembre de 2025
Número de páginas
8
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

VIRGINIA CONTRACTORS STUDY - A
& B LICENSE
The owner requests changes which will cost the contractor $2,500 in labor and materials and $700 in
overhead costs. With the change, the contractor would be relieved of $1,000 in labor costs and $280
in overhead costs from the original contract. The original bid included profit of 10% of all costs. The
contractor wants to make a profit of 10% of all costs on the changes. The amount of the change
order should included a request of an additional.



A. $1820

B. $2,112

C. $3,200

D. $3,520 - ✔✔ correct answer B. $2,112



A lump sum contract on a project has a total contract price of $200,000. Retainage has been held
back at 10%. The contractor has received progress payments of 90% of the project. The contractor
submits a request for the final payment for the now completed project. The final payment amount
should be for



A. less than 25,000$

b. between 25,000$ & 35,000$

c. between 35,000$ & 40,000$

d. more than 40,000$ - ✔✔ correct answer c. between 35,000$ & 40,000$



A contractor agrees to unit price contract to Product A fir $50 per unit, product B for $50 per unit,
and product C for $375 per unit. The contractor is also to add 30% for overhead and profit. How
much the contractor should be paid for producing 27 units of product A, 56 units of product B and 78
units of product C?



a. less than 40,000$

b. between 40,000$ & 45,000$

c. between 45,000 & 50,000$

d. more than 50,000$ - ✔✔ correct answer b. between 40,000$ & 45,000$



A contract calls for liquidated damage of 500$ per day. The project completed five days late because
it was delayed by rain. The completion would have been 10 days earlier if it were not for the rain

, VIRGINIA CONTRACTORS STUDY - A
& B LICENSE
delay. There was a 500$ bonus per day for the contractor early completion. No extension of time was
requested or granted. How much does the contractor earn or owe?



a. owes 2,500 in liquidated damage

b. owes 500 in liquidated damage

c. is due a 2,500 bonus from the owner

d. is due a 500 bonus from the owner - ✔✔ correct answer



A job has a price of 165,000 after direct costs and overhead are factored. What will the final bid be if
the profit markup is 11.5%



a. 186,440

b. 183,975

c. 179,545

d. 189,874 - ✔✔ correct answer a. 186,440



Give the following information, is it advantageous to purchase or rent this particular piece of
equipment if it has 3 useful years?



purchase rent

Initial cost 10,000 0

rental 0 550

salvage value 2,0000 0

insurance 40 0

operating costs 200 0




a. renting saves 840

b. renting saves 2,280

c. purchasing saves 840
$18.49
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
brittton phoenix
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
150
Miembro desde
2 año
Número de seguidores
95
Documentos
5175
Última venta
3 semanas hace
BRITTTON PRESENTS YOU WITH QUALITY EXAM,TESTBANKS AND ASSIGNMENTS

providing high quality grades is my all time priority, welcome to the world of super grades All The Best!!!!

3.3

19 reseñas

5
6
4
3
3
5
2
1
1
4

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes