The ________ will serve as the Initial Decision Maker, unless otherwise indicated in
the Agreement :
A) Owner
B) Architect
C) Construction Manager
D) Contractor Ans: Architect
MasterFormat provides a standard system for:
A) Numbering and titling Section paragraphs.
B) Assigning Work to Subcontractors or trades.
C) Titling and arranging Project Manuals.
D) Establishing construction sequence. Ans: C
Quality Control activities occur before or while accomplishing the Work or service:
A) True
B) False Ans: False
The parties to the Contract for Construction are:
A) Contractor and Subcontractors
,B) Owner
C) Architect
D) Contractor
E) Owner, Contractor and A/E
F) Suppliers or Manufacturers
G) Owner and Contractor Ans: G Owner and Contractor
One of the benefits of working as a team is not:
- increased productivity
- reducted project costs
- earlier project completion
- fewer meetings Ans: fewer meetings
The method of computation of Contractor's overhead and profits for Change Order
prices, where both additions and deletions are involved, is found in the:
A) Agreement.
B) Conditions of the Contract.
C) Division 1.
D) Instructions to Bidders. Ans: B Conditions of the Contract
The EPA's definition of a green building covers all three primary aspects of the built
environment, siting, design and construction.
© Get it right 2025 Getaway - Stuvia US All rights reserved
,True
False Ans: False
What functional considerations must the A/E use to design the project elements and
their relationships in a manner that ensures proper function of the project in
accordance with the Owner's program and related AHJ requirements?
A)
Adjacency of project elements, contextual compatibility of materials, aesthetic effects
of project elements
B)
Contractor's ability to procure the materials, owners programmatic requirements
C)
Quantities and arrangements of elements, juxtaposition of light and shadow
D)
The size of project elements, performance capacity of project elements, arrangement
of project elements Ans: D) The size of project elements, performance capacity of
project elements, arrangement of project elements
The Contractor team participants do NOT include the:
A) subcontractor.
B) Construction Manager.
© Get it right 2025 Getaway - Stuvia US All rights reserved
, C) Contractor.
D) Owner.
E) accountant Ans: D) Owner.
All of the following could be Articles in PART 1 - GENERAL of a specification except
which one?
A) References
B) Action Submittals
C) Source Quality Control
D) Measurement and Payment Ans: C) Source Quality Control
The responsibility of inspecting work already performed for proper condition to
receive subsequent work lies with the:
A) Owner
B) A/E
C) Contractor
D) Subcontractor Ans: C) Contractor
Division-01 sections of the Project Manual expand and cross reference the conditions
of the Contract in all cases.
© Get it right 2025 Getaway - Stuvia US All rights reserved