Congestion management 15 minutes
requests in Eastern
Interconnection from one RC
to
another must be implemented
how quickly
Voltage deviation of >/= 10% 15 minutes
nominal is reportable after
how long
Uncontrollable loss of 15 minutes
firm load for how long is
reportable (previous
years peak demand
>3000; >/+300mw -
otherwise 200mw)
Transmission & generator 10 minutes
data including status,
output capability, output,
phase angle settings, avr
status, etc. should be
updated every how
many minutes
If BA denies interchange, 10 minutes
they have how long to
notify RC
Default ramp rate for for 10 minutes
Eastern
Interconnection interchange
schedules
Unscheduled flow 5 minutes
transmission relief
, requested by the TOP
should be approved by the
RC how quickly
Ramp for interchange 5 minutes
schedules starts how soon
before start of schedule
Multiple contingencies within 1 minute
how many minutes of each
other are reported as a single
contingency
MW reportable threshold for 2000mw
sudden loss of gen
Ace calculation occurs how 6 seconds
often
When EEA3 is terminated, the 2 business days
EDE should submit a report to
the RC how soon after
termination/downgrading
How often is ATC for next 31 24 hours/daily
days calculated
When a reportable threshold 24 hours/next business day
has been
met, the responsible entity
has how long to report
GOP with blackstart resource 24 hours
must notify TOP of any
change to capabilities
affecting ability to meet
restoration plan within how
long of the change
RC/BA/TOP should test 90 calendar days
primary control center data
exchange capabilities for
redundant functionality at
least how often