1. What is the main responsibility of a Site Safety Manager on a construction
site in New York City?
A. Designing building blueprints
B. Ensuring compliance with NYC DOB safety regulations
C. Supervising all trade workers
D. Preparing structural load calculations
Rationale: Site Safety Managers focus on enforcing safety compliance with
NYC DOB and OSHA regulations.
2. The NYC DOB requires a Site Safety Plan to be submitted for buildings that
are how many stories or higher?
A. 5 stories
B. 10 stories
C. 15 stories
D. 20 stories
Rationale: NYC Building Code mandates a Site Safety Plan for construction
projects 15 stories or more.
3. The acronym SWPPP stands for:
A. Safe Work Place Plan
B. Safety Work Permit Program
C. Storm Water Pollution Prevention Plan
D. Site Worker Protection Plan
, Rationale: SWPPP addresses runoff and pollution control from construction
activities.
4. Which OSHA standard primarily governs fall protection?
A. 1910 Subpart Z
B. 1910.134
C. 1926 Subpart M
D. 1926.650
Rationale: OSHA 1926 Subpart M sets requirements for fall protection
systems in construction.
5. How often must a Site Safety Manager inspect active construction sites?
A. Once per month
B. Once per week
C. Daily
D. Twice per week
Rationale: Daily inspections are required by NYC DOB for active construction
sites under a safety plan.
6. When must a pre-shift safety meeting be conducted?
A. Weekly
B. Monthly
C. Before the start of each shift
D. Only after incidents
Rationale: Pre-shift meetings ensure all workers are briefed on hazards and
safety protocols.
7. A Controlled Access Zone (CAZ) is used to:
A. Store hazardous materials
B. Limit access to areas where overhead work is occurring
C. Train new workers
D. Mark exits
Rationale: CAZs are used to protect workers from hazards above or
restricted operations.
, 8. Which document details the emergency response procedures on a
construction site?
A. Permit Log
B. Daily Inspection Report
C. Site Safety Plan
D. Job Hazard Analysis
Rationale: The Site Safety Plan contains the project’s specific emergency
response strategy.
9. The NYC DOB requires that safety logs be maintained for how long on site?
A. 1 month
B. 3 years
C. 6 months
D. 5 years
Rationale: Records of inspections and incidents must be available for DOB
review for 3 years.
10.When using a crane, which credential must the operator hold in NYC?
A. OSHA 30-hour card
B. DOB Scaffold Card
C. NYC Crane Operator License
D. CDL Class A
Rationale: Only licensed crane operators with NYC DOB credentials may
operate cranes.
11.What is the minimum required clearance distance from energized power
lines up to 50 kV?
A. 5 feet
B. 8 feet
C. 10 feet
D. 15 feet
Rationale: OSHA 1926.1408 mandates a 10-foot clearance for lines up to 50
kV.