CONSTRUCTION MANAGEMENT
PRACTICE TEST WITH ALL NEEDED
TO PASS
Based gon gthe gguide gquantity gof g100 gCY gon ga gbid gdocument gfor grock
gexcavation, ga gcontractor gbid ga gunit gprice gof g$20/CY. gIf gthe gowner's
grepresentative gdetermined gthat gthe gcontractor gexcavated g85 gCY gof grock gduring
gconstruction, ghow gmuch gwill gthe gcontractor gget gpaid?
(a). g$2000
(b). g$1700
(c). g$300
(d). g$1800 g- gcorrect ganswers g-(b)
Which gof gthe gfollowing gdocuments gare gincluded gin gthe gbid gpackage?
, I. gProposal gForm
II. gSpecial gConditions
III. gTechnical gSpecifications
IV. gGeneral gConditions
V. gBid gBond
(a). gI, gII, gand gIII
(b). gII, gIII, gand gIV
(c). gI, gII, gIV, gand gV
(d). gI, gII, gIII, gand gIV g- gcorrect ganswers g-(d)
The gdocument grequested gby gthe gowner gas ga gprotection gagainst gthe grisk gof gthe
gcontractor gnot gaccepting gthe gjob gonce gawarded gthe gproject gis
(a). gInsurance
(b). gPerformance gBond
(c). gBid gBond
(d). gPayment gBond g- gcorrect ganswers g-(c)
Which gof gthe gfollowing gwould gnot gbe gconsidered gan gexcusable gdelay?
(a). gLabor gStrikes
(b). gReview gprocess gdelays
(c). gA ghurricane gclosing ga gport gdelaying gdelivery gof gmaterials
(d). gDeath gof ga gcontractor g- gcorrect ganswers g-(b)
The gtypically g30-90 gdays gperiod gafter gthe gbid gopening gwhere gthe gcontractor gis
gbound gby gtheir gbid gis gcalled
(a). gAcceptance gperiod
(b). gBid gperiod
(c). gAnxiety gperiod
(d). gRisk gperiod g- gcorrect ganswers g-(a)
The gprocedure gthat gallows ga gcontractor gto gpropose gchanges gto gthe gdesign gwith
gthe gapproval gof gthe gdesigner gto gsave gtime gand/or gmoney gis gcalled g
(a). gProcess gEngineering
(b). gValue gEngineering
(c). gDesign gbuild gengineering
(d). gCost gengineering g- gcorrect ganswers g-(b)
Which gof gthe gfollowing gdocuments gdetermines gthe gzero gday gof gthe gproject gfor
gscheduling gpurposes?
(a). gProposal gForm
(b). gFormal gcontract
(c). gNotice gto gbidders
(d). gNotice gto gproceed g- gcorrect ganswers g-(d)
The gamount gheld gback gfrom gthe gpayments gto ggive gthe gcontractor gan gincentive
gto gfinish gthe gjob gon gtime gis gcalled
PRACTICE TEST WITH ALL NEEDED
TO PASS
Based gon gthe gguide gquantity gof g100 gCY gon ga gbid gdocument gfor grock
gexcavation, ga gcontractor gbid ga gunit gprice gof g$20/CY. gIf gthe gowner's
grepresentative gdetermined gthat gthe gcontractor gexcavated g85 gCY gof grock gduring
gconstruction, ghow gmuch gwill gthe gcontractor gget gpaid?
(a). g$2000
(b). g$1700
(c). g$300
(d). g$1800 g- gcorrect ganswers g-(b)
Which gof gthe gfollowing gdocuments gare gincluded gin gthe gbid gpackage?
, I. gProposal gForm
II. gSpecial gConditions
III. gTechnical gSpecifications
IV. gGeneral gConditions
V. gBid gBond
(a). gI, gII, gand gIII
(b). gII, gIII, gand gIV
(c). gI, gII, gIV, gand gV
(d). gI, gII, gIII, gand gIV g- gcorrect ganswers g-(d)
The gdocument grequested gby gthe gowner gas ga gprotection gagainst gthe grisk gof gthe
gcontractor gnot gaccepting gthe gjob gonce gawarded gthe gproject gis
(a). gInsurance
(b). gPerformance gBond
(c). gBid gBond
(d). gPayment gBond g- gcorrect ganswers g-(c)
Which gof gthe gfollowing gwould gnot gbe gconsidered gan gexcusable gdelay?
(a). gLabor gStrikes
(b). gReview gprocess gdelays
(c). gA ghurricane gclosing ga gport gdelaying gdelivery gof gmaterials
(d). gDeath gof ga gcontractor g- gcorrect ganswers g-(b)
The gtypically g30-90 gdays gperiod gafter gthe gbid gopening gwhere gthe gcontractor gis
gbound gby gtheir gbid gis gcalled
(a). gAcceptance gperiod
(b). gBid gperiod
(c). gAnxiety gperiod
(d). gRisk gperiod g- gcorrect ganswers g-(a)
The gprocedure gthat gallows ga gcontractor gto gpropose gchanges gto gthe gdesign gwith
gthe gapproval gof gthe gdesigner gto gsave gtime gand/or gmoney gis gcalled g
(a). gProcess gEngineering
(b). gValue gEngineering
(c). gDesign gbuild gengineering
(d). gCost gengineering g- gcorrect ganswers g-(b)
Which gof gthe gfollowing gdocuments gdetermines gthe gzero gday gof gthe gproject gfor
gscheduling gpurposes?
(a). gProposal gForm
(b). gFormal gcontract
(c). gNotice gto gbidders
(d). gNotice gto gproceed g- gcorrect ganswers g-(d)
The gamount gheld gback gfrom gthe gpayments gto ggive gthe gcontractor gan gincentive
gto gfinish gthe gjob gon gtime gis gcalled