• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 3 out of 21 pages
Exam (elaborations)

Construction Manager – Ccm (Certified Construction Manager) Exam Questions And Correct Answers (Verified Answers) Plus Rationales 2025|2026 Q&A | Instantdownload Pdf

Document preview thumbnail
Preview 3 out of 21 pages

Construction Manager – Ccm (Certified Construction Manager) Exam Questions And Correct Answers (Verified Answers) Plus Rationales 2025|2026 Q&A | Instantdownload Pdf

Content preview

Construction Manager – Ccm (Certified Construction Manager)
Exam Questions And Correct Answers (Verified Answers) Plus
Rationales 2025|2026 Q&A | Instantdownload Pdf


Q1. Which of the following is the primary responsibility of a Certified
Construction Manager?
A. Minimize contractor profit
B. Protect the owner’s interests
C. Deliver the project safely, on time, within budget, and to quality standards
D. Maximize subcontractor productivity
The CCM’s role is to manage the entire process to meet the owner’s project
objectives (scope, cost, time, quality, safety).
Q2. The CMAA Code of Ethics requires CMs to:
A. Place employer’s profit above public safety
B. Disregard conflicts of interest if disclosed
C. Serve the client honestly and protect public health, safety, and welfare
D. Act as advocates for contractors
Ethics require prioritizing safety, honesty, and transparency in all actions.
Q3. Which document establishes the legal authority and obligations of a CM?
A. Project Charter
B. Project Manual
C. CM Services Agreement
D. Owner’s Schedule
The CM’s contract with the owner defines roles, duties, and legal obligations.
Q4. A conflict of interest occurs when:
A. The CM disagrees with the contractor
B. The CM misses a schedule milestone
C. The CM has a financial interest in a subcontractor being selected
D. The CM enforces contract terms
Conflicts of interest involve personal gain conflicting with professional duty.

,Q5. Which is the best dispute resolution method to preserve relationships?
A. Litigation
B. Mediation
C. Arbitration
D. Termination
Mediation is non-binding and promotes collaborative resolution.


Project Management
Q6. The triple constraint in project management includes:
A. Time, Profit, Communication
B. Scope, Risk, Safety
C. Scope, Time, Cost
D. Contract, Schedule, Quality
The classic project management triangle focuses on scope, cost, and schedule.
Q7. Which project delivery method gives the owner single-point responsibility?
A. Design-Bid-Build
B. Design-Build
C. CM as Agent
D. Multiple Prime Contracts
In design-build, one entity holds both design and construction contracts.
Q8. In risk management, the most effective strategy is:
A. Transfer all risks to the contractor
B. Identify and mitigate risks early in planning
C. Ignore low-probability risks
D. Eliminate owner involvement
Proactive risk planning is most effective to reduce impact.
Q9. A key benefit of Value Engineering (VE) is:
A. Accelerating schedule only
B. Improving function while reducing life-cycle cost
C. Eliminating project scope
D. Avoiding quality inspections
VE focuses on cost-effective design without sacrificing function.

, Q10. A Request for Information (RFI) is used primarily to:
A. Change the contract terms
B. Authorize payment
C. Seek clarification of design documents
D. Revise the CPM schedule
RFIs clarify drawings/specs during construction.


Contract Administration
Q11. Which contract type places the highest risk on the contractor?
A. Cost Plus Fixed Fee
B. Time and Materials
C. Lump Sum / Fixed Price
D. Guaranteed Maximum Price
In lump sum, contractor must complete work for a fixed amount.
Q12. A change order must include:
A. Contractor’s profit only
B. Updated daily logs
C. Scope, cost, and schedule adjustments
D. Only owner’s approval
Change orders modify contract terms for scope, cost, and time.
Q13. What is the primary purpose of retainage?
A. Provide CM contingency
B. Pay subcontractors early
C. Ensure contractor completes work properly
D. Accelerate project closeout
Retainage protects the owner by withholding funds until satisfactory completion.
Q14. The Notice to Proceed (NTP) establishes:
A. Contract completion
B. Official start date of construction work
C. Date of substantial completion
D. Owner’s final acceptance
NTP triggers the start of the contractor’s performance period.

Document information

Uploaded on
October 13, 2025
Number of pages
21
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$21.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
YouTubes
3.6
(37)
Sold
216
Followers
2
Items
5465
Last sold
3 days ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions