The amount the sponsor has agreed to pay for acceptable project deliverables is the
project budget (T/F) - ANSWERTrue
The project objective requires completing the project work scope on time and within the
budget (T/F) - ANSWERTrue
A person or organization responsible for each work item hsould be identified to assign
responsibility while planning the project (T/F) - ANSWERTrue
A project is completed through a number of repetitive tasks (T/F) - ANSWERFalse
The project scope document should include a list of deliverables and associated
acceptance criteria (T/F) - ANSWERTrue
People are the only resource used in a project. - ANSWERFalse
A project is carried out through a series of independent tasks (T/F) - ANSWERFalse
Projects are constrained only by the scope, schedule, and budget (T/F) -
ANSWERFalse
The project objective requires completing the project work scope and producing all the
deliverables by a certain time and within budget (T/F) - ANSWERTrue
A project is completed through a number of repetitive tasks (T/F) - ANSWERFalse
The project objective is usually defined in terms of end product, schedule, and budget
(T/F) - ANSWERTrue
A request for proposals (RFP) is used to initiate all projects by communicating that a
project is needed (T/F) - ANSWERFalse
A person or organizatoin responsible for each work item should be identified to assign
responsibility while planning the project (T/F) - ANSWERTrue
The level of effort is the same for all four phases of the generic project life cycle (T/F) -
ANSWERFalse
A project is an endeavor to accomplish a specific objective through a unique set of
interrelated tasks and the effective utilization of resources (T/F) - ANSWERTrue
ANSWERS(RATED A)
The amount the sponsor has agreed to pay for acceptable project deliverables is the
project budget (T/F) - ANSWERTrue
The project objective requires completing the project work scope on time and within the
budget (T/F) - ANSWERTrue
A person or organization responsible for each work item hsould be identified to assign
responsibility while planning the project (T/F) - ANSWERTrue
A project is completed through a number of repetitive tasks (T/F) - ANSWERFalse
The project scope document should include a list of deliverables and associated
acceptance criteria (T/F) - ANSWERTrue
People are the only resource used in a project. - ANSWERFalse
A project is carried out through a series of independent tasks (T/F) - ANSWERFalse
Projects are constrained only by the scope, schedule, and budget (T/F) -
ANSWERFalse
The project objective requires completing the project work scope and producing all the
deliverables by a certain time and within budget (T/F) - ANSWERTrue
A project is completed through a number of repetitive tasks (T/F) - ANSWERFalse
The project objective is usually defined in terms of end product, schedule, and budget
(T/F) - ANSWERTrue
A request for proposals (RFP) is used to initiate all projects by communicating that a
project is needed (T/F) - ANSWERFalse
A person or organizatoin responsible for each work item should be identified to assign
responsibility while planning the project (T/F) - ANSWERTrue
The level of effort is the same for all four phases of the generic project life cycle (T/F) -
ANSWERFalse
A project is an endeavor to accomplish a specific objective through a unique set of
interrelated tasks and the effective utilization of resources (T/F) - ANSWERTrue