Erosion and Sedimentation Pollution
Control (Study Guide #19) well
answered
Which of the below would require an approved erosion and sedimentation control plan before
any clearing or grading may occur? - correct answer ✔✔ over 1 acre
Erosion and sedimentation control plans must be submitted how many days in advance of the
start of clearing or grading? - correct answer ✔✔ 30 days
Which of the below are true about erosion and sedimentation control? - correct answer ✔✔ all
of these
Who is responsible for erosion control? - correct answer ✔✔ Person financially responsible for
land disturbing activity
In addition to the person financially responsible for the land disturbing activity who else may be
held responsible for erosion control? - correct answer ✔✔ The land owner
After construction is complete who is responsible for maintenance and future compliance of
erosion control? - correct answer ✔✔ Land owner
A permanent ground cover, sufficient to control erosion, must be installed within which of the
below times after completion of construction or development? - correct answer ✔✔ 15 working
days or 90 calendar days
What is the minimum a sediment basin (A temporary sediment trap) should hold per acre? -
correct answer ✔✔ 1800 cubic feet
Control (Study Guide #19) well
answered
Which of the below would require an approved erosion and sedimentation control plan before
any clearing or grading may occur? - correct answer ✔✔ over 1 acre
Erosion and sedimentation control plans must be submitted how many days in advance of the
start of clearing or grading? - correct answer ✔✔ 30 days
Which of the below are true about erosion and sedimentation control? - correct answer ✔✔ all
of these
Who is responsible for erosion control? - correct answer ✔✔ Person financially responsible for
land disturbing activity
In addition to the person financially responsible for the land disturbing activity who else may be
held responsible for erosion control? - correct answer ✔✔ The land owner
After construction is complete who is responsible for maintenance and future compliance of
erosion control? - correct answer ✔✔ Land owner
A permanent ground cover, sufficient to control erosion, must be installed within which of the
below times after completion of construction or development? - correct answer ✔✔ 15 working
days or 90 calendar days
What is the minimum a sediment basin (A temporary sediment trap) should hold per acre? -
correct answer ✔✔ 1800 cubic feet