When planning and designing the installation of new or replacement of existing
underground facilities, the designer follows all, except: - Answer-The routing demanded
by the local environmental association
The quality management system documentation shall include the following, except for: -
Answer-All federally required processes regarding the project at hand
Regarding design and development review, at suitable stages, review(s) shall be
performed: - Answer-To evaluate the suitability, adequacy, and effectiveness of the
results of design and development stages to meet specified requirements;
To identify any problems and propose necessary actions;
The Contingency Plan shall include the following, at a minimum: - Answer-Actions
required in response to significant risk scenarios to mitigate effects of disruptive
incidents;
Identification and assignment of responsibilities and authorities;
Internal and external communication controls
Where arc welding is regularly carried out, adjacent walls and other surfaces shall have:
- Answer-Low reflectivity to ultraviolet radiation
When using cleaning compounds prior to welding, __________ instructions shall be
followed - Answer-manufacturers
Using qualified ___________ ensures that all contractors who bid and work on a project
employ safe work habits and are capable of performing the requested work. - Answer-
contractors
Crossing Angle is the angle measured between the existing pipeline and the proposed
location of pipe and is recommended to be as close to _________ as practical. -
Answer-90 degrees
If air, natural gas, or inert gas is used as the test medium, the maximum hoop stress
limitations apply for a class 2 location: - Answer-Natural Gas = 30%, Air or Inert Gas =
75%
, All pipe must be installed so that when crossing a drainage ditch at public roads and
railroads, the minimum cover is ________ for normal excavation and _______ for rock
excavation. - Answer-36 inches, 36 inches
Rock excavation is any excavation that requires __________ or removal by equivalent
means. - Answer-blasting
Any pipe installed underground must have at least ______ inches of clearance between
the outside of the pipe and the extremity of any other underground structure (pipeline) -
Answer-12
The test pressure for each pressure test conducted under 195.304 must be maintained
throughout the part of the system being tested for _______ continuous hours at a
pressure equal to __________ percent, of more, of the maximum operating pressure. -
Answer-4, 125
Line markers are not required for - Answer-Offshore or at crossings of or under
waterways and other bodies of water.
In heavily developed urban areas such as downtown business centers where the
placement of markers and would not serve the purpose for which markers are intended.
Hot work means work that does not involve electric or gas welding, cutting, brazing, or
similar flame of spark-producing operations. - Answer-false
The ____________ shall verify that the required workplace hazard assessment has
been performed through a written certification that identifies the workplace evaluated;
the person certifying that the evaluation has been performed; the date(s) of the hazard
assessment; and, which identifies the document as a certification of hazard
assessment. - Answer-employer
Each ___________ shall be trained to know at least; when PPE is necessary; what PPE
is necessary; how to properly don, doff, adjust and wear PPE; the limitations of PPE;
and the proper care of PPE - Answer-inspector
Which one below is NOT considered a safe operating practice whenever a sling is
used?
Slings that are damaged or defective shall not be used - Answer-the cost of slings are
critical
The placement of a lockout device on an energy isolating device, in accordance with an
established procedure, ensuring that the energy isolating device and the equipment
being controlled cannot be operated until the lockout device is removed is called a
__________ - Answer-lockout
REVIEWED CORRECT DETAILED
ANSWERS
When planning and designing the installation of new or replacement of existing
underground facilities, the designer follows all, except: - Answer-The routing demanded
by the local environmental association
The quality management system documentation shall include the following, except for: -
Answer-All federally required processes regarding the project at hand
Regarding design and development review, at suitable stages, review(s) shall be
performed: - Answer-To evaluate the suitability, adequacy, and effectiveness of the
results of design and development stages to meet specified requirements;
To identify any problems and propose necessary actions;
The Contingency Plan shall include the following, at a minimum: - Answer-Actions
required in response to significant risk scenarios to mitigate effects of disruptive
incidents;
Identification and assignment of responsibilities and authorities;
Internal and external communication controls
Where arc welding is regularly carried out, adjacent walls and other surfaces shall have:
- Answer-Low reflectivity to ultraviolet radiation
When using cleaning compounds prior to welding, __________ instructions shall be
followed - Answer-manufacturers
Using qualified ___________ ensures that all contractors who bid and work on a project
employ safe work habits and are capable of performing the requested work. - Answer-
contractors
Crossing Angle is the angle measured between the existing pipeline and the proposed
location of pipe and is recommended to be as close to _________ as practical. -
Answer-90 degrees
If air, natural gas, or inert gas is used as the test medium, the maximum hoop stress
limitations apply for a class 2 location: - Answer-Natural Gas = 30%, Air or Inert Gas =
75%
, All pipe must be installed so that when crossing a drainage ditch at public roads and
railroads, the minimum cover is ________ for normal excavation and _______ for rock
excavation. - Answer-36 inches, 36 inches
Rock excavation is any excavation that requires __________ or removal by equivalent
means. - Answer-blasting
Any pipe installed underground must have at least ______ inches of clearance between
the outside of the pipe and the extremity of any other underground structure (pipeline) -
Answer-12
The test pressure for each pressure test conducted under 195.304 must be maintained
throughout the part of the system being tested for _______ continuous hours at a
pressure equal to __________ percent, of more, of the maximum operating pressure. -
Answer-4, 125
Line markers are not required for - Answer-Offshore or at crossings of or under
waterways and other bodies of water.
In heavily developed urban areas such as downtown business centers where the
placement of markers and would not serve the purpose for which markers are intended.
Hot work means work that does not involve electric or gas welding, cutting, brazing, or
similar flame of spark-producing operations. - Answer-false
The ____________ shall verify that the required workplace hazard assessment has
been performed through a written certification that identifies the workplace evaluated;
the person certifying that the evaluation has been performed; the date(s) of the hazard
assessment; and, which identifies the document as a certification of hazard
assessment. - Answer-employer
Each ___________ shall be trained to know at least; when PPE is necessary; what PPE
is necessary; how to properly don, doff, adjust and wear PPE; the limitations of PPE;
and the proper care of PPE - Answer-inspector
Which one below is NOT considered a safe operating practice whenever a sling is
used?
Slings that are damaged or defective shall not be used - Answer-the cost of slings are
critical
The placement of a lockout device on an energy isolating device, in accordance with an
established procedure, ensuring that the energy isolating device and the equipment
being controlled cannot be operated until the lockout device is removed is called a
__________ - Answer-lockout