Test Bank for Project Management in Practice 7th Edition by Jack R Meredith Scott M Shafer Complete Chapters PDF Download

Beoordeling
-
Verkocht
-
Pagina's
138
Cijfer
A+
Geüpload op
14-09-2025
Geschreven in
2025/2026

Test Bank for Project Management in Practice 7th Edition by Jack R Meredith Scott M Shafer Complete Chapters PDF Download

Instelling
Tests Bank 2025
Vak
Tests Bank 2025











Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
Tests Bank 2025
Vak
Tests Bank 2025

Documentinformatie

Geüpload op
14 september 2025
Aantal pagina's
138
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

Test Bank For
Project Management in Practice, 7th Edition Meredith
Chapter 1-8

Chapter 1: The World of Project Management
True/False
1. A primary purpose of forming projects is to assign the responsibility for
accomplishing some organizational task to a specific person or small group.

Answer: True
Response: See section 1.1
Level: easy



2. One of the few similarities between project management and general management
is that both exist in the well-defined organizational structure of
superior/subordinates in the overall organization.

Answer: False
Response: See section 1.2
Level: medium



3. Many recent developments in project management are being driven by changes in
the nature of the American workforce.

Answer: False
Response: See section 1.1
Level: medium



4. There has been a growing use of projects to achieve an organization’s strategic
goals

Answer: True
Response: See section 1.1
Level: medium




Copyright ©2017 John Wiley & Sons, Inc.

,5. While general managers have their authority limited to specific areas in the
overall organization, project managers have authority over any activity required
by the project.

Answer: False
Response: See section 1.2
Level: medium



6. Projects are always carried out under conditions of uncertainty.

Answer: True
Response: See section 1.3
Level: easy



7. One can trade-off time and cost when managing a project, but the project’s
technical specifications must be maintained exactly as the client initially specifies.

Answer: False
Response: See section 1.3
Level: medium



8. Nonnumeric project selection methods are only suitable if numeric methods are
not available.

Answer: False
Response: See section 1.5
Level: medium


9. When using financial methods for selecting projects, the payback period is the
simplest and best method to use.

Answer: False
Response: See section 1.5
Level: medium



10 Rank-ordering a large number of projects can be done with a Q-sort.



Copyright ©2017 John Wiley & Sons, Inc.

, Answer: True
Response: See section 1.5
Level: medium



11. A disadvantage of using the payback period method for selecting projects is that it
cannot reflect the time-value of money.

Answer: True
Response: See section 1.5
Level: medium




12. A disadvantage of using the discounted cash flow method (or net present value)
for selecting projects is that it ignores all non-monetary factors associated with the
project except risk.

Answer: True
Response: See section 1.5
Level: medium



13. A disadvantage of using scoring models rather than financial models for selecting
projects is that they cannot include the project’s profitability.

Answer: False
Response: See section 1.5
Level: medium



14. A PM does not need to understand why a project is selected for funding because
he did not initiate the process.

Answer: False
Response: See section 1.5
Level: medium



15. The main distinction between platform and breakthrough projects is that the
former usually depend on existing technology.


Copyright ©2017 John Wiley & Sons, Inc.

, Answer: True
Response: See section 1.6
Level: medium



16. The main distinction between platform and derivative projects is that the latter
depend on existing technology.

Answer: False
Response: See section 1.6
Level: medium




17. One reason for the emphasis on project management is that tasks fit neatly into
business-as-usual.

Answer: False
Response: See section 1.1
Level: easy



18. Programs are subdivisions of projects.

Answer: False
Response: See section 1.1
Level: easy



19. Projects are subdivisions of programs.

Answer: True
Response: See section 1.1
Level: easy



20. A similarity between project management and general management is the
tendency to ―manage by exception.‖


Copyright ©2017 John Wiley & Sons, Inc.

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
ExamCrafters Teachme2-tutor
Bekijk profiel
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
1366
Lid sinds
1 jaar
Aantal volgers
8
Documenten
1060
Laatst verkocht
1 maand geleden

4.6

262 beoordelingen

5
199
4
32
3
19
2
6
1
6

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via Bancontact, iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo eenvoudig kan het zijn.”

Alisha Student

Veelgestelde vragen