Project Management Chapter 6 Questions with Correct Answers A+

Institution
Project Management Chapter
Course
Project Management Chapter









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Project Management Chapter
Course
Project Management Chapter

Document information

Uploaded on
September 7, 2025
Number of pages
12
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Project Management Chapter 6 Questions
with Correct Answers A+
a. planning schedule management - ✔✔Which of the following processes involves determining

the policies, procedures, and documentation that will be used for planning, executing, and

controlling the project schedule?

a. planning schedule management

b. defining activities

c. estimating activity resources

d. activity sequencing



d. activity attributes - ✔✔Predecessors, successors, logical relationships, leads and lags, resource

requirements, constraints, imposed dates, and assumptions are all examples of .

a. items in an activity list

b. items on a Gantt chart

c. milestone attributes

d. activity attributes



c. discretionary - ✔✔As the project manager for a software development project, you are helping

to develop the project schedule. You decide that writing code for a system should not start until

users sign off on the analysis work. What type of dependency is this?

a. technical

b. mandatory

, c. discretionary

d. external



a. finish-to-start - ✔✔You cannot start editing a technical report until someone else completes

the first draft. What type of dependency does this represent?

a. finish-to-start

b. start-to-start

c. finish-to-finish

d. start-to-finish



b. Duration and effort are synonymous terms. - ✔✔Which of the following statements is false?

a. A resource breakdown structure is a hierarchical structure that identifies the project's resources

by category and type.

b. Duration and effort are synonymous terms.

c. A three-point estimate includes an optimistic, most likely, and pessimistic estimate.

d. A Gantt chart is a common tool for displaying project schedule information.



d. a white diamond - ✔✔What symbol on a Gantt chart represents a slipped milestone?

a. a black arrow

b. a white arrow

c. a black diamond

d. a white diamond
$15.29
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
Legitsolutionsstuvia

Get to know the seller

Seller avatar
Legitsolutionsstuvia Liberty University
View profile
Follow You need to be logged in order to follow users or courses
Sold
0
Member since
3 months
Number of followers
0
Documents
92
Last sold
-

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions