1. Tests that are unannounced, randomly performed, and
repeat quality control tests are: - ANSWER ✓ Quality
Assurance tests
2. If initial review of the Quality Control Plan shows it to
be unacceptable: - ANSWER ✓ The contractor makes
changes before acceptance.
3. The contractor quality control organization: - ANSWER
✓ May vary in size depending on the work being
performed at a point in time.
4. The Quality Control Plan contains: - ANSWER ✓
Identification of individual quality quality control
, personnel, including name, qualifications, assigned
duties, responsibilities and authorities.
5. The Preconstruction Conference and the Coordination
and Mutual Understanding Meeting (NAVFAC) are: -
ANSWER ✓ Conducted prior to the commencement of
any physical construction work.
6. Design-Build contracts require: - ANSWER ✓ The QC
Manager to be in place and take an active role in the
review and coordination of the design.
7. At what temperature are employers required to train
their workers on the effects of heat and methods of
protection? - ANSWER ✓ 80 degrees Fahrenheit
8. What does Whiting-Turner use to decide to take action
around air quality? - ANSWER ✓ The EPA Air Quality
Index