Questions and CORRECT Answers
_____ is a planning process that is within the Project Scope Management knowledge area.
Quality planning
Schedule development
Creation of a WBS
Developing a project management plan - CORRECT ANSWER - Creation of a WBS
Organizational process assets update is the output of the closing process of _____.
project integration management
project quality management
project time management
project procurement management - CORRECT ANSWER - project integration
management
The _____ provides a basis for creating the project schedule and performing earned value
management for measuring and forecasting project performance.
project charter
cost management plan
work breakdown structure
scope statement - CORRECT ANSWER - work breakdown structure
, The _____ process involves gaining stakeholder and customer acceptance of the final products
and services and bringing the project, or project phase, to an orderly end.
closing
monitoring
executing
planning - CORRECT ANSWER - closing
_____ includes measuring progress toward project objectives and taking corrective action to
match progress with the plan.
Planning
Monitoring and controlling
Initiating
Executing - CORRECT ANSWER - Monitoring and controlling
Examples of _____ processes include acquiring and developing the project team, performing
quality assurance, distributing information, managing stakeholder expectations, and conducting
procurements.
initiating
monitoring and controlling
planning
executing - CORRECT ANSWER - executing
Which of the following is true about the agile method?
It is used when project teams want to use the predicative approach to a project.