A Heavy Load Voltage Schedule Warning is typically issued ___ prior to actual implementation.
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
- correct answersc. 4 hours
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\
The following would be considered non-critical plant load (Select 2) - correct answersA. Office
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
Area Air Conditioners |||\\\ |||\\\
C. Lighting |||\\\
During a Cold Weather Alert, PJM will take which of the actions - correct answersD. Assume an
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
unavailability rate for schedule generation
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\
When PJM issues a High System Voltage Message, the GO should have its units operate at: -
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
correct answersB. The lower end of their voltage bandwidth |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
What would the reportable Emergency Reducible Generation be if the Generator Output is 400
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
MW, Economic Min is 225 MW and the Emergency Min is 175 MW - correct answersC. 50 MW
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
PJM can issue the Deploy All Resources Action for - correct answersD. The entire RTO, specific
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
Control Zones, or a subset of a Control Zone if transmission limitations exist |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
PJM has issued a Minimum Generation Alert. Your current generation is 200 MW. The Economic
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
Minimum is 150 MW and the Emergency Min is 125 MW. How much ERG should be reported
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
for this unit? - correct answersB. 25MW
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
Which of the following steps would PJM take as part of initiating Conservative Operations?
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
(Select 2) - correct answersA. Perform job studies looking at the loss of multiple pieces of
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
equipment as a single event |||\\\ |||\\\ |||\\\ |||\\\
,C. Initiate additional off-cost operation to limit or reduce flows across critical interfaces
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
The purpose of the Deploy All Resources Action is to instruct all generating resources to be on
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
line and at full output ____ - correct answersD. Immediately upon receipt of dispatch
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
instructions
Under the National Terrorism Advisory System (NTAS) there are two types of alerts: Elevated
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
Threat Alert and - correct answersA. Imminent Threat Alert |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
What is the requested response time for members to reply to a request for SSR data? - correct
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
answersA. 10 minutes |||\\\ |||\\\
You are a Generation Owner with the following units. PJM has just requested a Supplementary
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
Status Report (SSR). what do you report as your total "On Cost" Steam Capacity
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
U1: ECO max, 145 - EMR max 145 Current output 140
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
U2 ECO max, 550 - EMR max 145 Current output 400
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
U3 ECO max, 400, EMR max 410 Current output - correct answers1095MW
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
Why does PJM require an additional notification time of Unit testing 30 minutes prior to the
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
GO/MOC performing the reactive capability testing? - correct answersC. To allow PJM and TOs |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
to make adjustments to system voltages prior to test
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
When an outage requires verbal notification to PJM which PJM personnel should be contacted?
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
- correct answersB. Master Coordinator
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
One of the leading causes of the 1999 Low Voltage event in PJM was ___ - correct answersB.
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
PJM's EMS at that time had only nameplate D-curve data for |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
, With whom does PJM share the results of generation reactive capability tests? - correct
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
answersA. The affected TO |||\\\ |||\\\ |||\\\
With the exception of intermittent resources, Over-excited (Lagging) test results are the values
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
of MVAR output that can be sustained for how long? - correct answersD. 60 min
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
During the PJM Peak Period Maintenance Season whit is the max amount of consecutive days
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
the outage can last? - correct answersC. 9
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
When PJM requests a Reactive Reserve Check (RRC), how does the GO/MOC report limitations
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
or restrictions on their unit which would prevent it from being able to follow it's reactive
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
capability curve as recorded in eDART - correct answersA. By notifying the effect TO |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
What is the min time needed to submit a reactive capability test ticket via eDARt prior to
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
performing the test? - correct answersC. 3 business days |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
A unit (or intermittent facility) will be considered as having passed their capability test and
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
require no further action if their test results are within ___ of the stated limits - correct
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
answersD. 5% |||\\\
Even if no changes are made, MOCs/GOs must review and confirm their unit reactive capability
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
via eDARt how ofter? - correct answersD. Twice per year
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
What is the penalty for units that do not meet their stated reactive capability during reactive
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
capability - correct answersB. There is no penalty |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
When submitted expected capability for "new" units, what reactive capability should be used? -
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
correct answersB. Vendor supplied D-curves
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
correct answers |||\\\
A Heavy Load Voltage Schedule Warning is typically issued ___ prior to actual implementation.
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
- correct answersc. 4 hours
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\
The following would be considered non-critical plant load (Select 2) - correct answersA. Office
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
Area Air Conditioners |||\\\ |||\\\
C. Lighting |||\\\
During a Cold Weather Alert, PJM will take which of the actions - correct answersD. Assume an
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
unavailability rate for schedule generation
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\
When PJM issues a High System Voltage Message, the GO should have its units operate at: -
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
correct answersB. The lower end of their voltage bandwidth |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
What would the reportable Emergency Reducible Generation be if the Generator Output is 400
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
MW, Economic Min is 225 MW and the Emergency Min is 175 MW - correct answersC. 50 MW
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
PJM can issue the Deploy All Resources Action for - correct answersD. The entire RTO, specific
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
Control Zones, or a subset of a Control Zone if transmission limitations exist |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
PJM has issued a Minimum Generation Alert. Your current generation is 200 MW. The Economic
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
Minimum is 150 MW and the Emergency Min is 125 MW. How much ERG should be reported
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
for this unit? - correct answersB. 25MW
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
Which of the following steps would PJM take as part of initiating Conservative Operations?
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
(Select 2) - correct answersA. Perform job studies looking at the loss of multiple pieces of
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
equipment as a single event |||\\\ |||\\\ |||\\\ |||\\\
,C. Initiate additional off-cost operation to limit or reduce flows across critical interfaces
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
The purpose of the Deploy All Resources Action is to instruct all generating resources to be on
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
line and at full output ____ - correct answersD. Immediately upon receipt of dispatch
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
instructions
Under the National Terrorism Advisory System (NTAS) there are two types of alerts: Elevated
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
Threat Alert and - correct answersA. Imminent Threat Alert |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
What is the requested response time for members to reply to a request for SSR data? - correct
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
answersA. 10 minutes |||\\\ |||\\\
You are a Generation Owner with the following units. PJM has just requested a Supplementary
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
Status Report (SSR). what do you report as your total "On Cost" Steam Capacity
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
U1: ECO max, 145 - EMR max 145 Current output 140
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
U2 ECO max, 550 - EMR max 145 Current output 400
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
U3 ECO max, 400, EMR max 410 Current output - correct answers1095MW
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
Why does PJM require an additional notification time of Unit testing 30 minutes prior to the
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
GO/MOC performing the reactive capability testing? - correct answersC. To allow PJM and TOs |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
to make adjustments to system voltages prior to test
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
When an outage requires verbal notification to PJM which PJM personnel should be contacted?
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
- correct answersB. Master Coordinator
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
One of the leading causes of the 1999 Low Voltage event in PJM was ___ - correct answersB.
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
PJM's EMS at that time had only nameplate D-curve data for |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
, With whom does PJM share the results of generation reactive capability tests? - correct
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
answersA. The affected TO |||\\\ |||\\\ |||\\\
With the exception of intermittent resources, Over-excited (Lagging) test results are the values
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
of MVAR output that can be sustained for how long? - correct answersD. 60 min
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
During the PJM Peak Period Maintenance Season whit is the max amount of consecutive days
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
the outage can last? - correct answersC. 9
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
When PJM requests a Reactive Reserve Check (RRC), how does the GO/MOC report limitations
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
or restrictions on their unit which would prevent it from being able to follow it's reactive
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
capability curve as recorded in eDART - correct answersA. By notifying the effect TO |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
What is the min time needed to submit a reactive capability test ticket via eDARt prior to
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
performing the test? - correct answersC. 3 business days |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
A unit (or intermittent facility) will be considered as having passed their capability test and
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
require no further action if their test results are within ___ of the stated limits - correct
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
answersD. 5% |||\\\
Even if no changes are made, MOCs/GOs must review and confirm their unit reactive capability
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
via eDARt how ofter? - correct answersD. Twice per year
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
What is the penalty for units that do not meet their stated reactive capability during reactive
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
capability - correct answersB. There is no penalty |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
When submitted expected capability for "new" units, what reactive capability should be used? -
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\
correct answersB. Vendor supplied D-curves
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\