PJM Generation Dispatch Exam Flash |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




Cards exam with correct answers |||\\\ |||\\\ |||\\\ |||\\\




Which of the following statements is correct concerning PJM assuming frequency control of the
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




restoration process?
|||\\\ |||\\\




A) PJM assumes control once an external transmission tie has been established.
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




B) Once an Area Control Error can be calculated, PJM will assume control.
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




C) Whenever it becomes too much of a burden for any one Transmission Owner within the RTO
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




D) Whenever the Transmission Owners within the RTO agree to let PJM control the process. -
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




correct answersC) Whenever it becomes too much of a burden for any one Transmission
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




Owner within the RTO |||\\\ |||\\\ |||\\\




During black start restoration, priority access to cranking power should be given to:
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




A) Hot units that can return to service immediately.
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




B) Combustion turbines in areas where the initial disturbance occurred
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




C)Units with black start capability |||\\\ |||\\\ |||\\\ |||\\\




D) Hydro Units - correct answersA) Hot units that can return to service immediately.
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




During a restoration, if you are presented with the opportunity to re-connect with the Eastern
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




Interconnection, you should: |||\\\ |||\\\




A)Not pursue this opportunity because you may cause the Eastern Interconnection to become
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




unstable.

B) Pursue this opportunity only when you have adequate Dynamic Reserves on your system
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\

,C) Pursue this opportunity as quickly as possible
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




D) Pursue this opportunity only if you need cranking power for your generating unity - correct
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




answersC) Pursue this opportunity as quickly as possible |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




Complete (Total System) Blackouts are characterized by which of the following? |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




1 - Most common type of blackout
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




2 - May require coordinating multiple islands
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




3 - Likely to result in Transmission overloads or other issues
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




4 - Affects a very large geographical area, and many customers
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




5 - Most commonly caused by human or switching errors
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




A) 1 & 3 |||\\\ |||\\\ |||\\\




B) 2 & 4 |||\\\ |||\\\ |||\\\




C) 3 & 5 |||\\\ |||\\\ |||\\\




D) 1 - correct answersB) 2 & 4
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




The first step in a system restoration would be to:
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




A) Immediately notify the media of the event
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




B) Restore as much of the area load as possible
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




C) Restore as much under-frequency load as possible
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




D) Verify that communication is functional with your neighbors - correct answersD) Verify that
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




communication is functional with your neighbors |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




Why would an offsite power to generating facilities be a priority during the restoration
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




process?

,A) To provide safe shutdown power for the units
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




B) To meet FERC requirements
|||\\\ |||\\\ |||\\\ |||\\\




C) To provide adequate lighting for the plant operators to attempt a restart
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




D) To prepare and expedite the return of the unit - correct answersD) To prepare and expedite
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




the return of the unit |||\\\ |||\\\ |||\\\ |||\\\




Factors that help determine the sequence of restoration of off-line generation include (Pick 2):
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




-Generation Type |||\\\




-Unloaded Capacity |||\\\




-Unit Availability |||\\\




-Stability of the Generator - correct answers-Generation Type |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




-Unit Availability |||\\\




How often should a Transmission company file an updated restoration report with PJM?
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




1 - Every 30 minutes
|||\\\ |||\\\ |||\\\ |||\\\




2 - Every hour
|||\\\ |||\\\ |||\\\




3 - Every 10 lines that have been restored
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




4 - Every 5 lines that have been restored
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




A) 1 & 4 |||\\\ |||\\\ |||\\\




B) 2 & 3 |||\\\ |||\\\ |||\\\




C) 1 & 3 |||\\\ |||\\\ |||\\\




D) 2 & 4 - correct answersC) 1 & 3
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\

, Which of the following statements are true concerning delays in restoring auxiliary power to
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




off-line generation? |||\\\




1 - The unit could suffer turbine shaft damage
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




2 - The fuel oil for the unit could congeal
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




3 - The startup time for the unit will be reduced
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




4 - The battery life used to maintain critical systems may run out
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




A) 1, 2 and 3 |||\\\ |||\\\ |||\\\ |||\\\




B) 1, 2 and 4 |||\\\ |||\\\ |||\\\ |||\\\




C) 1, 3 and 4 |||\\\ |||\\\ |||\\\ |||\\\




D) 2, 3 and 4 - correct answersB) 1, 2 and 4
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




During system restoration, the two categories of reserves are:
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




A) dynamic and secondary
|||\\\ |||\\\ |||\\\




B) spinning and quick start
|||\\\ |||\\\ |||\\\ |||\\\




C) dynamic and spinning
|||\\\ |||\\\ |||\\\




D) spinning and primary - correct answersC) dynamic and spinning
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




During a system restoration you have 400MW of Steam capacity, 350MW of CT capacity and
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




300MW of Hydro capacity restored. Your largest contingency is a 200MW Steam Unit. You have
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




also restored 150MW of under-frequency load. What is your total dynamic reserve? (Load
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




pick-up factors are 5% for steam, 15% for hydro and 25% for CT)
|||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\ |||\\\




A) 142.5MW |||\\\

Document information

Uploaded on
August 29, 2025
Number of pages
69
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$11.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
progrades
4.0
(2)
Sold
14
Followers
0
Items
3893
Last sold
1 month ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions