When preparing for a procurement that can only be purchased from a
single source, the _________ document is required. - ANSWERS-
justification and approval
There are two basic contract types, cost reimbursement and fixed-price.
All others, with the exception of a time-and-materials contract which is a
hybrid of the two, are subsets of cost reimbursement or fixed-price
contracts. Which of the following is NOT true? - ANSWERS-cost
reimbursement contracts require less monitoring by the COR than other
types of contracts
The purpose of market research is to determine capabilities in the
marketplace able to satisfy the government's needs. - ANSWERS-True
Acquisition Planning begins when the agency's need is identified. Which
of the following is TRUE regarding requirements development and
documentation? - ANSWERS-The requirements document should use
market research and promote full...
Major sub-categories of funding include: - ANSWERS-All the answers
are correct
END OF
PAGE
1
, CLC-222 LATEST
CONTRACTING
EXAM
An Accounting Classification Requirements Number (ACRN) is: -
ANSWERS-All these responses are correct
The main purpose for the COR to understand the contract and how it is
organized is to be aware of all contractual requirements and deliverables.
This knowledge helps the COR track contractor performance and ensure
contractor compliance with the contract as written. - ANSWERS-True
The COR has identified a change to the contract that will increase costs.
What steps must be taken for the Contracting Officer to modify the
contract? - ANSWERS-Identify the change to the contract, complete a
technical evaluation of the contractor's proposal, develop the estimated
cost
Contracting Officer's Representatives do not have authority to modify
the contract; however, they are vital to the process as they are relied
upon to notify the Contracting Officer of required contract changes and
evaluating proposals. - ANSWERS-True
END OF
PAGE
2
, CLC-222 LATEST
CONTRACTING
EXAM
During negotiations for a proposed change to the contract, the COR may
be asked to: - ANSWERS-All correct
John, the COR on a services contract, has made an unauthorized
commitment by authorizing the contractor to perform services that were
not within the scope of the contract. Choose the true statement from the
following: - ANSWERS-A contracting officer may ratify an
unauthorized commitment if the government received a benefit...
An option is the unilateral right of the government to extend or buy more
than the amounts bought at the time of award. - ANSWERS-True
The COR should only use formal communication when working with a
contractor. - ANSWERS-false
The COR must be careful when giving technical direction to ________.
- ANSWERS-Clarify the intent of the requirements without impacting
cost
END OF
PAGE
3
CONTRACTING
EXAM
When preparing for a procurement that can only be purchased from a
single source, the _________ document is required. - ANSWERS-
justification and approval
There are two basic contract types, cost reimbursement and fixed-price.
All others, with the exception of a time-and-materials contract which is a
hybrid of the two, are subsets of cost reimbursement or fixed-price
contracts. Which of the following is NOT true? - ANSWERS-cost
reimbursement contracts require less monitoring by the COR than other
types of contracts
The purpose of market research is to determine capabilities in the
marketplace able to satisfy the government's needs. - ANSWERS-True
Acquisition Planning begins when the agency's need is identified. Which
of the following is TRUE regarding requirements development and
documentation? - ANSWERS-The requirements document should use
market research and promote full...
Major sub-categories of funding include: - ANSWERS-All the answers
are correct
END OF
PAGE
1
, CLC-222 LATEST
CONTRACTING
EXAM
An Accounting Classification Requirements Number (ACRN) is: -
ANSWERS-All these responses are correct
The main purpose for the COR to understand the contract and how it is
organized is to be aware of all contractual requirements and deliverables.
This knowledge helps the COR track contractor performance and ensure
contractor compliance with the contract as written. - ANSWERS-True
The COR has identified a change to the contract that will increase costs.
What steps must be taken for the Contracting Officer to modify the
contract? - ANSWERS-Identify the change to the contract, complete a
technical evaluation of the contractor's proposal, develop the estimated
cost
Contracting Officer's Representatives do not have authority to modify
the contract; however, they are vital to the process as they are relied
upon to notify the Contracting Officer of required contract changes and
evaluating proposals. - ANSWERS-True
END OF
PAGE
2
, CLC-222 LATEST
CONTRACTING
EXAM
During negotiations for a proposed change to the contract, the COR may
be asked to: - ANSWERS-All correct
John, the COR on a services contract, has made an unauthorized
commitment by authorizing the contractor to perform services that were
not within the scope of the contract. Choose the true statement from the
following: - ANSWERS-A contracting officer may ratify an
unauthorized commitment if the government received a benefit...
An option is the unilateral right of the government to extend or buy more
than the amounts bought at the time of award. - ANSWERS-True
The COR should only use formal communication when working with a
contractor. - ANSWERS-false
The COR must be careful when giving technical direction to ________.
- ANSWERS-Clarify the intent of the requirements without impacting
cost