COSC 354 Project Management Exam #3 Questions and Answers Already Passed Latest Update Steps involved in the planning and scheduling process - Answers - Establish Project Objective(s) - Typically owner driven - Identify Project Tasks/Activities (definable work activities) - Determine Task/Activity Sequence (what activity must proceed and what activity must succeed?) - Determine Task/Activity Durations (the estimate can be very helpful here) - Perform Schedule calculations (if using CPM) to determine the project's Critical Path - Revise and Adjust the Schedule (Could the duration be shortened to take advantage of a bonus for finishing early?) - Monitor and Control against the baseline or target schedule (the goal is to stay on target and finish the project on time!) Scheduling throughout the project (preconstruction, construction, and postconstruction) - Answers Preconstruction Phase: - Planning and scheduling is a key activity during this phase - Project financing, commitments to the owner, and market projections all depend upon the scheduled start and completion date - The initial schedule should be viewed as an opportunity to build the project on paper and help the project team to begin making intelligent management decisions - As the project evolves, the team will continually refine the schedule to optimize the project activity durations Construction Phase: - Schedules are essential to the successful coordination of a project's day-to-day operations (material, equipment, and labor) - As a project progresses, delays will occur! Anticipate delays and be ready to effectively deal with them. - Job progress is closely tracked, and the schedule is often placed on the wall of the job office/trailer where it is clearly visible to everyone (which Lean Builder tool is this?) Postconstruction Phase: - In this final phase, the schedule can be used to coordinate and control when the owner begins to occupy the facility - Most projects require testing and acceptance of equipment and systems (remember commissioning?) and training of end users. The schedule can be helpful in this regard as well! - Lastly, postconstruction scheduling can be part of an effective recordkeeping program for "after action" reviews so that better planning and scheduling can occur on future projects The types of schedules and the pros/cons of each - Answers Bar Charts: Graphically Represents: - Planned overall length of project - Planned duration of each major project component

Content preview

COSC 354 Project Management Exam #3 Questions and Answers Already Passed Latest
Update 2025-2026

Steps involved in the planning and scheduling process - Answers - Establish Project Objective(s)
- Typically owner driven

- Identify Project Tasks/Activities (definable work activities)

- Determine Task/Activity Sequence (what activity must proceed and what activity must
succeed?)

- Determine Task/Activity Durations (the estimate can be very helpful here)

- Perform Schedule calculations (if using CPM) to determine the project's Critical Path

- Revise and Adjust the Schedule (Could the duration be shortened to take advantage of a bonus
for finishing early?)

- Monitor and Control against the baseline or target schedule (the goal is to stay on target and
finish the project on time!)

Scheduling throughout the project (preconstruction, construction, and postconstruction) -
Answers Preconstruction Phase:

- Planning and scheduling is a key activity during this phase

- Project financing, commitments to the owner, and market projections all depend upon the
scheduled start and completion date

- The initial schedule should be viewed as an opportunity to build the project on paper and help
the project team to begin making intelligent management decisions

- As the project evolves, the team will continually refine the schedule to optimize the project
activity durations



Construction Phase:

- Schedules are essential to the successful coordination of a project's day-to-day operations
(material, equipment, and labor)

- As a project progresses, delays will occur! Anticipate delays and be ready to effectively deal
with them.

- Job progress is closely tracked, and the schedule is often placed on the wall of the job
office/trailer where it is clearly visible to everyone (which Lean Builder tool is this?)

, Postconstruction Phase:

- In this final phase, the schedule can be used to coordinate and control when the owner begins
to occupy the facility

- Most projects require testing and acceptance of equipment and systems (remember
commissioning?) and training of end users. The schedule can be helpful in this regard as well!

- Lastly, postconstruction scheduling can be part of an effective recordkeeping program for
"after action" reviews so that better planning and scheduling can occur on future projects

The types of schedules and the pros/cons of each - Answers Bar Charts: Graphically Represents:

- Planned overall length of project

- Planned duration of each major project component

- Calendar start and finish dates for each project phase Advantages

- Simple and quick to produce

- Simple to read/comprehend

- Good for executive review and public meetings Disadvantages

- Does not communicate the interrelationships among project activities



Matrix Schedule:

- Typically used for repetitive work, such as multi-story buildings

- A good tool for communicating/controlling field activities because it can be posted in the job
office and updated as work progresses

Advantages

- Easily understood by nontechnical people

- Best when used as a coordination tool in the field

Disadvantages

- Lacks detail

- does not typically consider all project activities

Document information

Uploaded on
August 20, 2025
Number of pages
12
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$10.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TutorJosh
3.5
(76)
Sold
493
Followers
16
Items
32839
Last sold
3 hours ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions