HSI Final Test Questions With Correct
Answers

The initial response to a frequency deviation is due to which of the following
| | | | | | | | | | | | |




1. Load / frequency response
| | | | |




2. AGC
|




3. Governor action
| |




4. Interchange schedules
| |




•3 and 4
| |




•1 and 2
| |




•2 and 3
| |




•1 and 3 - CORRECT ANSWER✔✔-•1 and 3
| | | | | | |




EMS and AGC have failed at 12:25 and generation must be controlled manually.
| | | | | | | | | | | | |


The operator calculates ACE to be +25 MWs. Load is expected to increase 100
| | | | | | | | | | | | | |


MWs, and imports will increase by 75 MWs at the top of the hour. What should
| | | | | | | | | | | | | | | |


the operator do?
| |




•Maintain current generation level | | |




•Decrease generation by 25 MWs | | | |




•Decrease generation by 50 MWs | | | |

,•Increase generation by 25 MW - CORRECT ANSWER✔✔-•Decrease generation
| | | | | | | | |


by 25 MWs
| |




How is the Frequency Response Measure (FRM) of a Balancing Authority
| | | | | | | | | | |


determined?


•lt is the average of the BA's frequency response for all the frequency deviations
| | | | | | | | | | | | | |


of the previous year
| | |




•lt is the change in the BA's Net Interchange Actual for the largest frequency
| | | | | | | | | | | | | |


deviation during the previous year | | | |




•lt is the previous year's Control Performance Standard 1 ( CPS1 ) score
| | | | | | | | | | | |




•It is the median of the BA's frequency response for the frequency deviation
| | | | | | | | | | | | |


events identified by NERC for the previous year - CORRECT ANSWER✔✔-•It is the
| | | | | | | | | | | | |


median of the BA's frequency response for the frequency deviation events
| | | | | | | | | | |


identified by NERC for the previous year | | | | | |




Sufficient Operating Reserve is defined as the capacity required to meet what?
| | | | | | | | | | |




•DOE specifications |




•CPS and DCS | |




•CPS 1 & 2 only | | | |




•Capacity Standard - CORRECT ANSWER✔✔-•CPS and DCS
| | | | | |




In your Interconnection , a generator tripped that was large enough to reduce the
| | | | | | | | | | | | |


|frequency from 60.00 Hz to 59.94 Hz . Your Balancing Authority's Frequency Bias
| | | | | | | | | | | | |

,is -200 MW / 0.1 Hz . How many MW would your system initially contribute to
| | | | | | | | | | | | | | | |


frequency support? |




•120 MW |




•80 MW|




•100 MW |




•200 MW - CORRECT ANSWER✔✔-•120 MW
| | | | |




Interconnection frequency is 59.80 Hz . Your ACE is a large negative value and
| | | | | | | | | | | | | |


your AGC is pulsing your units down . What should you do
| | | | | | | | | | |




•Leave AGC in operation but investigate
| | | | |




•Place AGC in constant frequency control
| | | | |




•Place AGC in flat tie line control
| | | | | |




•Suspend AGC and investigate - CORRECT ANSWER✔✔-•Suspend AGC and
| | | | | | | | |


investigate


When a Balancing Authority's ACE value is the same sign as the frequency
| | | | | | | | | | | | |


deviation , which NERC control performance score is affected negatively
| | | | | | | | |




•DCS
•CPS 1 |




•TEC
•BAAL - CORRECT ANSWER✔✔-•CPS 1
| | | |

, Correct Of the following , which control system would be affected by a difference
| | | | | | | | | | | | | |


in Net Actual Interchange and Net Scheduled Interchange
| | | | | | |




•Reactive Control |




•Turbine Governor Control | |




•Automatic Generation Control | |




•Automatic Voltage Regulator - CORRECT ANSWER✔✔-•Automatic Generation
| | | | | | |


Control


Balancing Authority A is currently reading a system frequency of 59.98 Hz . Its Net
| | | | | | | | | | | | | |


|Actual Interchange is +100 MW and its Net Scheduled Interchange is +100 MW .
| | | | | | | | | | | | | |


If Balancing Authority A's frequency bias setting is 100 MW / 0.1 HZ , what is ACE
| | | | | | | | | | | | | | | |




• -20
|




•20
•2
•0 - CORRECT ANSWER✔✔-• -20
| | | |




A Balancing Authority has twenty units on governor control . The units have
| | | | | | | | | | | | |


different capacities that range from 200 MW to 1000 MW and droop settings
| | | | | | | | | | | | |


from 2 % to 5 % . The biggest adjustments in megawatt output in response to a
| | | | | | | | | | | | | | | | |


frequency disturbance will be provided by units that have _______________?
| | | | | | | | |




•large capacity and small droop setting
| | | | |

Document information

Uploaded on
August 20, 2025
Number of pages
39
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$18.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Lectphilip
4.1
(43)
Sold
273
Followers
6
Items
25746
Last sold
13 hours ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions