,_____ level of masterformat is reserved for assignment - CORRECT ANSWERS-fourth
_______ _______ _______A detailed, time sensitive study of the volume of flow of
information (voice, data, video) over a network system. This document will allow the
client to assess network bandwidth usage. - CORRECT ANSWERS-Network Traffic
Studies
___________ are used to visually document critical components at completion of
installation. - CORRECT ANSWERS-Photographs
_____level of masterformat is reserved for user definition - CORRECT ANSWERS-fifth
A _____________________ outlines the processes required to certify and deliver a
complete and functioning system to the client. - CORRECT ANSWERS-commissioning
plan
A commissioning plan should document: - CORRECT ANSWERS-• Administration:
- Labeling of all components.
- O&M documentation.
• Cleaning.
• Testing, adjusting, and settings.
• Training client personnel.
• Warranty time period and licensing.
Acceptance Plan - CORRECT ANSWERS-Outlines the tasks, tools, staff, and skills
necessary to test and document the successful completion of a project.
Activities of Post Construction Include: - CORRECT ANSWERS-Cutover (As soon as
construction completed)
Training owner personnel on use and adjustment
Warranty inspection
Operations and Maintenance begin before Post construction ends
As Builts incorporated into CAFM
Final Payments anf release of retainage
Actual Costs (AC) - CORRECT ANSWERS-Amount of money it took to accomplish the
work that was completed.
Goal should be to = PV
AIA CAD Layer Guidelines - CORRECT ANSWERS-Introduction - Overview/ History/
Highlights
Layer Name Format - Concept/ Guidelines
Layer List - Guidelines for all 23 Layers
Commentary ISO/ NCS
AIA produced - CORRECT ANSWERS-Computer Aided Design guidelines
, Analogus Estimates - CORRECT ANSWERS-Based on similar work done in the past
Archictect Role During Post Construction - CORRECT ANSWERS-Final Acceptance,
prepare punch list, update as builts
Architect - CORRECT ANSWERS-Lead design professional, hired by the owner
Are periodic progress reports considered deliverables? - CORRECT ANSWERS-NO
As Built Drawing Contents - CORRECT ANSWERS-Pathways
Cable
Telecommunication Spaces
Work Area Outlets
At the initial stage of construction the GC typically holds two meetings - CORRECT
ANSWERS-1) With Owner and Design Team
2) Field Personnel and subcontractor
AV System Depicts - CORRECT ANSWERS-Audio flow
Video flow
Remote control system connection
Simplified line drawings
Basic Planning of the SoW - CORRECT ANSWERS-Answer the "why" and "what"
Bottom-Up Estimates - CORRECT ANSWERS-Uses WBS Tasks
Building Profile and floor to floor relationship within each building - CORRECT
ANSWERS-Project Drawing - Cross Sections
Change Control System - CORRECT ANSWERS-Any change order or add service
should be identified
Change Order - CORRECT ANSWERS-Formal document defining changes to scope
and identifies associated changes to time frame/ dollar amounts or both
Change Order Contents - CORRECT ANSWERS-• Date and time submitted.
• Detailed description of change request.
• Requestor's name.
• Written authorization to proceed.
• Date and time approval received.
Change Order Request - CORRECT ANSWERS-Contractor submits to field order for
change to scope
Study Questions and Answers | Grade A | 100%
Correct (Verified Solutions)
,_____ level of masterformat is reserved for assignment - CORRECT ANSWERS-fourth
_______ _______ _______A detailed, time sensitive study of the volume of flow of
information (voice, data, video) over a network system. This document will allow the
client to assess network bandwidth usage. - CORRECT ANSWERS-Network Traffic
Studies
___________ are used to visually document critical components at completion of
installation. - CORRECT ANSWERS-Photographs
_____level of masterformat is reserved for user definition - CORRECT ANSWERS-fifth
A _____________________ outlines the processes required to certify and deliver a
complete and functioning system to the client. - CORRECT ANSWERS-commissioning
plan
A commissioning plan should document: - CORRECT ANSWERS-• Administration:
- Labeling of all components.
- O&M documentation.
• Cleaning.
• Testing, adjusting, and settings.
• Training client personnel.
• Warranty time period and licensing.
Acceptance Plan - CORRECT ANSWERS-Outlines the tasks, tools, staff, and skills
necessary to test and document the successful completion of a project.
Activities of Post Construction Include: - CORRECT ANSWERS-Cutover (As soon as
construction completed)
Training owner personnel on use and adjustment
Warranty inspection
Operations and Maintenance begin before Post construction ends
As Builts incorporated into CAFM
Final Payments anf release of retainage
Actual Costs (AC) - CORRECT ANSWERS-Amount of money it took to accomplish the
work that was completed.
Goal should be to = PV
AIA CAD Layer Guidelines - CORRECT ANSWERS-Introduction - Overview/ History/
Highlights
Layer Name Format - Concept/ Guidelines
Layer List - Guidelines for all 23 Layers
Commentary ISO/ NCS
AIA produced - CORRECT ANSWERS-Computer Aided Design guidelines
, Analogus Estimates - CORRECT ANSWERS-Based on similar work done in the past
Archictect Role During Post Construction - CORRECT ANSWERS-Final Acceptance,
prepare punch list, update as builts
Architect - CORRECT ANSWERS-Lead design professional, hired by the owner
Are periodic progress reports considered deliverables? - CORRECT ANSWERS-NO
As Built Drawing Contents - CORRECT ANSWERS-Pathways
Cable
Telecommunication Spaces
Work Area Outlets
At the initial stage of construction the GC typically holds two meetings - CORRECT
ANSWERS-1) With Owner and Design Team
2) Field Personnel and subcontractor
AV System Depicts - CORRECT ANSWERS-Audio flow
Video flow
Remote control system connection
Simplified line drawings
Basic Planning of the SoW - CORRECT ANSWERS-Answer the "why" and "what"
Bottom-Up Estimates - CORRECT ANSWERS-Uses WBS Tasks
Building Profile and floor to floor relationship within each building - CORRECT
ANSWERS-Project Drawing - Cross Sections
Change Control System - CORRECT ANSWERS-Any change order or add service
should be identified
Change Order - CORRECT ANSWERS-Formal document defining changes to scope
and identifies associated changes to time frame/ dollar amounts or both
Change Order Contents - CORRECT ANSWERS-• Date and time submitted.
• Detailed description of change request.
• Requestor's name.
• Written authorization to proceed.
• Date and time approval received.
Change Order Request - CORRECT ANSWERS-Contractor submits to field order for
change to scope