Final Estimates 2 FDOT
Save
Terms in this set (7)
1. Special Provisions
2. Technical Special Provisions
What is the governing 3. Plans
order of contract 4. Design Standards
documents? 5. Developmental Specifications
6. Supplemental Specifications
7. Standard specification
What are the resources 1. Standard Specifications
used for Conventional 2. Basis of Estimates (BOE) Manual
Contracts? 3. Construction Project Administration Manual (CPAM)
Which of these is a 1. Standard Specifications
contract Document:
1. Standard Specifications
2. Basis of Estimates (BOE)
Manual
3. Construction Project
Administration Manual
(CPAM)
Monthly payments are A Contractor's Monthly Estimate
based on:
Once the contract is 1. Supplemental Agreements (SA)
executed, the only way to 2. Work Orders (WO)
modify the contract 3. Unilateral Payment
document is through: