Stockpiles of aggregate Minimize Free Water Content
shall be maintained in a
well-drained condition in
order to:
Coarse aggregate 24
stockpiles must be
sprinkled for at lest how
many hours prior to batch
for FDOT?
Free moisture of the Moister on the surface of an aggregate that is above
aggregate means: and beyond the absorbed moister in the aggregate.
If the moister test is done Each week
other than by the cook-
out method, how often
shall the other methods
be verified?
For drill shaft concrete, 33 thru 37%
the quantity of cement
replaced with fly ash shall
be:
In concrete, which Water
material has a specific
gravity of one?
https://quizlet.com/1064557156/concrete-batch-plant-operator-exam-fdot-flash-cards/?new 1/7
, 8/8/25, 8:39 AM Concrete Batch Plant Operator Exam (FDOT) Flashcards | Quizlet
What is the air content 1.00 thru 6.00%
range for all classes of
structural concrete except
Class IV Shaft?
When can unmetered Not at all.
water be added to the
concrete?
Do not allow the total 160 Revolutions
number of revolution at
mixing speed to exceed:
After all materials have 70 to 100
been charged into the
transit mixer drum, the
concrete must be mixed at
how many revolutions at
the plant before leaving
for the project?
When the water meters / 3 moths
scales are calibrated, prior
to production, at what
frequency should they be
checked there after?
To what accuracy should 0.5% of maximum load normally handled
the scales for weighing
cement , pozzolan, slag
and aggregates at the
plant be maintained
For concrete containing a 90 minutes
water-reducing retarding
admixture, in an agitator
truck, the maximum time
for depositing the
concrete shall not exceed: