Which perspective of an organization focuses on different groups' roles and
responsibilities in order to meet the goals and policies set by top management?
a.Symbolic frame
b.Human resources frame
c.Structural frame
d.Political frame - -c.Structural frame
-Work performance information and cost forecasts are main outputs of which
process?
a.cost budgeting
b.cost pricing
c.cost estimating
d.cost control - -d.cost control
-Which process involves gaining stakeholder and customer acceptance of the final
products and services and bringing the project, or project phase, to an orderly end?
a.planning
b.monitoring
c.executing
d.closing - -closing-- The closing process involves gaining stakeholder and customer
acceptance of the final products and services and then bringing the project or
project phase to an orderly end. It includes verifying that all of the deliverables are
complete, and it often includes a final project report and presentation.
-What term is used for the amount of time an activity can be delayed from its early
start without delaying the planned project finish date?
a.backward pass
b.free float
c.forward pass
d.total slack - -d.total slack
-After identifying the major risks and allocating priorities in the software project
that you are busy with, your next responsibility is to decide how to deal with these
risks and allocate their priorities. Which of the following contain the most
appropriate option you would consider?
a.Risk acceptance, risk assurance, risk transfer and avoidance
b.Risk acceptance, risk reduction, and mitigation, risk assessment and risk transfer
c.Risk assurance, risk assessment, risk transfer and risk avoidance
d.Risk acceptance, risk reduction and mitigation, risk avoidance and risk transfer - -
-Which project management knowledge area primarily involves generating,
collecting, disseminating, and storing project information?
Which perspective of an organization focuses on different groups' roles and
responsibilities in order to meet the goals and policies set by top management?
a.Symbolic frame
b.Human resources frame
c.Structural frame
d.Political frame - -c.Structural frame
-Work performance information and cost forecasts are main outputs of which
process?
a.cost budgeting
b.cost pricing
c.cost estimating
d.cost control - -d.cost control
-Which process involves gaining stakeholder and customer acceptance of the final
products and services and bringing the project, or project phase, to an orderly end?
a.planning
b.monitoring
c.executing
d.closing - -closing-- The closing process involves gaining stakeholder and customer
acceptance of the final products and services and then bringing the project or
project phase to an orderly end. It includes verifying that all of the deliverables are
complete, and it often includes a final project report and presentation.
-What term is used for the amount of time an activity can be delayed from its early
start without delaying the planned project finish date?
a.backward pass
b.free float
c.forward pass
d.total slack - -d.total slack
-After identifying the major risks and allocating priorities in the software project
that you are busy with, your next responsibility is to decide how to deal with these
risks and allocate their priorities. Which of the following contain the most
appropriate option you would consider?
a.Risk acceptance, risk assurance, risk transfer and avoidance
b.Risk acceptance, risk reduction, and mitigation, risk assessment and risk transfer
c.Risk assurance, risk assessment, risk transfer and risk avoidance
d.Risk acceptance, risk reduction and mitigation, risk avoidance and risk transfer - -
-Which project management knowledge area primarily involves generating,
collecting, disseminating, and storing project information?