NR 425 FINAL questions with accurate answers
4 Step Process of Adaptive Management Ans✓✓✓ 1. Develop
mitigation with future condition or performance standards included
2. Implement mitigation
3. Monitor to determine success
4. Adjust, as necessary
5 Mitigation Measures Ans✓✓✓ 1. Avoid
2. Minimize
3. Rectify
4. Reduce and Eliminate
5. Compensate
Adaptive Management Ans✓✓✓ Based on the idea that mitigation
should be adapted over time depending on how well measures are
actually working
Alternatives Analysis Ans✓✓✓ Select a reasonable range that
1. Meets most of the basic project objectives
2. Substantially lessens one or more significant impacts
3. Are potentially feasible
4. Must include a no project alternative
, Approaches to Significance Criteria Ans✓✓✓ - Environmental
Standards: Thresholds established for other environmental
permits/regulations
- Significance Criteria from other Environmental Documents
- Stakeholder Input and Polling
- Original Investigations
CA Coastal Commission Ans✓✓✓ - Coastal Zone
- If development is within the Coastal Zone, a Coastal Development
Permit is required
CA State Lands Commission Ans✓✓✓ - In charge of managing
"public trust" or "sovereign" lands
Case Law for Essential Nexus Ans✓✓✓ Nollan
Case Law for Roughly Proportional Mitigations Ans✓✓✓ Dolan
CEQA Process Overview Ans✓✓✓ 1. Preliminary Review
2. Initial Study
3. ND or EIR
4. Decision Documentation
4 Step Process of Adaptive Management Ans✓✓✓ 1. Develop
mitigation with future condition or performance standards included
2. Implement mitigation
3. Monitor to determine success
4. Adjust, as necessary
5 Mitigation Measures Ans✓✓✓ 1. Avoid
2. Minimize
3. Rectify
4. Reduce and Eliminate
5. Compensate
Adaptive Management Ans✓✓✓ Based on the idea that mitigation
should be adapted over time depending on how well measures are
actually working
Alternatives Analysis Ans✓✓✓ Select a reasonable range that
1. Meets most of the basic project objectives
2. Substantially lessens one or more significant impacts
3. Are potentially feasible
4. Must include a no project alternative
, Approaches to Significance Criteria Ans✓✓✓ - Environmental
Standards: Thresholds established for other environmental
permits/regulations
- Significance Criteria from other Environmental Documents
- Stakeholder Input and Polling
- Original Investigations
CA Coastal Commission Ans✓✓✓ - Coastal Zone
- If development is within the Coastal Zone, a Coastal Development
Permit is required
CA State Lands Commission Ans✓✓✓ - In charge of managing
"public trust" or "sovereign" lands
Case Law for Essential Nexus Ans✓✓✓ Nollan
Case Law for Roughly Proportional Mitigations Ans✓✓✓ Dolan
CEQA Process Overview Ans✓✓✓ 1. Preliminary Review
2. Initial Study
3. ND or EIR
4. Decision Documentation