Whose responsibility is it to review past performance during the Pre-Award phase? -
ANSWERSContracting Officer (KO)
___________ is the Preferred method because it puts the risk on the contractor and has
measurable metrics and milestones which incentivize a contractor. -
ANSWERSPerformance Work Statement (PWS).
What might cause restrictive language in a requirements document? - ANSWERSLack
of flexibility and competition (ambiguity)
_____________are detailed descriptions telling the contractor what to do and how to do
it. - ANSWERSStatement of Work
Type of requirement might be listed on a DA 3953• - ANSWERS• A description of what
is to be acquired
• Fund citation
• Required delivery dates
• Delivery or performance location
• Requiring activity point of contact
What document describes the required supplies or services so procurement can be
initiated? - ANSWERSPurchase Request
Types of requirement documents and the order of precedence? - ANSWERS1.
Documents mandated for use by law. (Market research)
2. Performance-oriented documents.
(e.g., a PWS or SOO).
(3) Detailed design-oriented documents.
(4) Standards, specifications and related publications issued by the Government outside
the Defense or Federal series for the non-repetitive acquisition of items.
Funding restriction _______ is if funds are not obligated during their period of
availability, they expire and are unavailable for new obligations. - ANSWERSTime
Funding restriction _______ is when funds must be expended for the purpose
established by Congress. - ANSWERSPurpose
, Funding restriction _________ is the Anti-Deficiency Act prohibits obligating or spending
money before it is appropriated or in amounts in excess of the amount appropriated. -
ANSWERSAmount
What are the 3 types of specification? - ANSWERS1. Design Specification
2. Functional Specifications
3. Performance Specifications
_________________ Specification Identify requirements by specifying exact
dimensions, materials, composition, physical and chemical requirements and other
details of the product or service. - ANSWERSDesign
States only the end result to be achieved (Environmental control method that will
maintain temp between 70 and 78 degrees) - ANSWERSFunctional Specifications
Expresses requirements in the form of output, function or operation of a commodity. -
ANSWERSPerformance Specifications
FAR 37.603 states that performance standards establish required performance level
that must be __________ and __________. - ANSWERSMeasurable and Structured
Types of Requirements Documents: - ANSWERS- Commercial Item Descriptions (CID)
- Statement of Work (SOW)
- Performance Work Statement (PWS) / Statement of Objectives (SOO)- Specifications
- Government Standard
- Industry Standard
Simplified product descriptions that describe commercial items that are available to
meet the Government's needs - ANSWERSCommercial Item Description
A _____________provides established measures of quality, or requirements for
materials, engineering practices, performance, design or operation -
ANSWERSGovernment Standard
____________________ are established by a private sector to promote commonality
and establishes common requirements. Products may or may not adhere to an industry
standard. - ANSWERSIndustry Standard
Where is GFP Clause located in the FAR? - ANSWERSFAR 52.245-1
______________ means property in the possession of, or directly acquired by, the
Government and subsequently furnished to the Contractor for performance of a
contract.