The ______ consists of daily checks of the work to assure continuing compliance with contract
requirements correct answers Follow-up phase
Design-Build contracts require: correct answers *The QC Manager to be in place and take an
active role in the review and coordination of the design*
Which of the following is included in all three phases of the Three Phases of Control correct
answers Safety
The purpose of Construction Quality Management is to correct answers *Achieve the quality
established by properly developed requirements through the combined responsibility, but
separate, efforts of contractor and Government personnel*
Testing is extremely important in Construction Quality Management and is performed by correct
answers Both the contractor and the Government
The primary purpose of the Three-Phase Control System is to: correct answers Require the
contractor to plan, schedule, and perform quality management actions to assure work meets all
specified quality standards
Quality Assurance Personnel have the responsibility to: correct answers *require the contractor
to maintain the quality specified in the plans and specifications*
the ____ is the appropriate time to assure that all materials and/or equipment have been tested.
submitted, and approved. correct answers Preparatory Phase
The Preconstruction Conference and the Coordination and Mutual Understanding Meeting are:
correct answers conducted prior to the commencement of any physical construction work
, Contractor testing procedures: correct answers are specified in the technical specifications,
outlined in the Quality Control Plan, and addressed at the Coordination and Mutual
Understanding Meeting.
The Quality Control Plan contains: correct answers Identification of individual quality control
personnel, including name, qualifications, assigned duties, responsibilities and authorities
Tests that are unnanounced, randomly performed, and repeat quality control tests are: correct
answers quality assurance tests
The contractor is required to conduct a preparatory phase meeting before they begins any
definable feature of work except when: correct answers there are no exceptions to the rule
During the punch-out inspection of a project: correct answers *Quality control personnel prepare
a punch-list and make corrections*
The Quality Control Report should include: correct answers All of the above :
Work in Progress
Work that has been completed
Problem areas
In a design-build contract, if the contractor has a question about the design, what is the process to
get an answer? correct answers *Contractor submits a design verification request to the
contractor's design team.*
Submittals are: correct answers Necessary to demonstrate that the proposed materials, etc. are in
compliance with the contract.
The success or failure of all contractors is based upon: correct answers The ability to control
costs, finance work, estimate jobs, schedule the work and maintain effective quality control