CM 413 JOBSITE FINAL EXAM 2025
QUESTIONS WITH 100% CORRECT
ANSWERS!!
1 of 48
Definition
Contractor
Give this one a try later!
Which of the following is NOT a factor inherently involved in the design loads,
allowable stresses, and safety factors used for the design of various structures:
, Aspects of temporary structures, such as design, allowable stresses and
loads, materials, and inspection, the permanent structure.
A contractor for simple temporary structures has to submit detailed plans,
prepared or checked and signed by a licensed professional engineer.
If the owner of a project did not retain supervision of the contractor, who
would be held liable to damage to a building adjacent to the construction
project?
Don't know?
2 of 48
Term
Building codes and standards are largely silent on temporary
structures and the technical literature is scant on the subject.
Give this one a try later!
True 27 Units
OSHA 24"
Don't know?
3 of 48
, Definition
27 Units
Give this one a try later!
How much was the construction How many housing units does
budget for the Coast Hills Project? the Academy at Chorro have?
What was the final project cost What is the size of the Promenade
at the Academy at Chorro? project?
Don't know?
4 of 48
Definition
True
Give this one a try later!
Failure to comply with the Temporary support and access
federal code can subject the structures have a critical effect
contractor to substantial civil on the__of construction
penalties by_________________? projects.
Injuries due to falls count for Liability arising from plans and
what percentage of injuries in design is usually excluded
the construction industry each from most owners' and
year?
contractors' liability insurance.
QUESTIONS WITH 100% CORRECT
ANSWERS!!
1 of 48
Definition
Contractor
Give this one a try later!
Which of the following is NOT a factor inherently involved in the design loads,
allowable stresses, and safety factors used for the design of various structures:
, Aspects of temporary structures, such as design, allowable stresses and
loads, materials, and inspection, the permanent structure.
A contractor for simple temporary structures has to submit detailed plans,
prepared or checked and signed by a licensed professional engineer.
If the owner of a project did not retain supervision of the contractor, who
would be held liable to damage to a building adjacent to the construction
project?
Don't know?
2 of 48
Term
Building codes and standards are largely silent on temporary
structures and the technical literature is scant on the subject.
Give this one a try later!
True 27 Units
OSHA 24"
Don't know?
3 of 48
, Definition
27 Units
Give this one a try later!
How much was the construction How many housing units does
budget for the Coast Hills Project? the Academy at Chorro have?
What was the final project cost What is the size of the Promenade
at the Academy at Chorro? project?
Don't know?
4 of 48
Definition
True
Give this one a try later!
Failure to comply with the Temporary support and access
federal code can subject the structures have a critical effect
contractor to substantial civil on the__of construction
penalties by_________________? projects.
Injuries due to falls count for Liability arising from plans and
what percentage of injuries in design is usually excluded
the construction industry each from most owners' and
year?
contractors' liability insurance.