Accurate Answers
____________ is defined as covering work whose component activities are less
defined and whose
interrelationships are conditional.
A. Soft logic
B. Hard logic
C. Deductive logic
D. Inductive logic correct answer Answer: A
____________ is the application of total resources ($-workers-supports) and
activity durations of the logic
diagram.
A. Planning
B. Forecasting
C. Scheduling
D. Modeling correct answer Answer: C
______________can be defined as the determination of that course of action or
combination of alternatives that
yields either the lowest cost or the highest profit.
A. Economic optimization
,B. Simulation
C. Linear programming
D. Dynamic programming correct answer Answer: D
_____________is defined as the budget for the cost (work) account times the
percent complete for that account.
A. Percent complete
B. Forecast
C. Cost to complete
D. Earned value correct answer Answer: D
____________is defined as the earned work hours or dollars for all accounts
divided by the budgeted work
hours or dollars for all accounts.
A. Percent complete
B. Cost to complete
C. Earned value
D. Forecast correct answer Answer: A
A bond that guarantees the bidder will enter into a contract on the basis of
his/her bid is referred to as:
A. Surety bond
,B. Performance bond
C. Bid bond
D. Liability bond correct answer Answer: C
A concrete slab measuring 10 feet wide by 13.5 feet long by 6 inches deep is to be
installed. How many cubic
yards of concrete will be required?
A. 3.0 cubic yards
B. 2.0 cubic yards
C. 3.5 cubic yards
D. 2.5 cubic yards correct answer Answer: D
A contract clause that provides the owner with the right to terminate the contract
irrespective of the general
contractor's liability is:
A. Termination of contract - convenience
B. Termination of contract - default
C. Substantial completion
D. Breach of contract correct answer Answer: A
A major theme park is expanding the existing facility over a five-year period. The
design phase will be
completed one year after the contract is awarded. Major engineering drawings
will be finalized two years after
, the design contract is awarded and construction will begin three years after the
award of the design contract.
New, unique ride technology
will be used and an estimate will need to be developed to identify these costs that
have no historical data.
According to Maslow's hierarchy of needs, which level should be satisfied first?
A. Physiological
B. Self-actualization
C. Safety needs
D. Ego-status correct answer Answer: C
A major theme park is expanding the existing facility over a five-year period. The
design phase will be
completed one year after the contract is awarded. Major engineering drawings
will be finalized two years after
the design contract is awarded and construction will begin three years after the
award of the design contract.
New, unique ride technology
will be used and an estimate will need to be developed to identify these costs that
have no historical data.
After an individual's safety needs are met, what needs would the individual be
motivated to fulfill next in
Maslow's hierarchy of needs?
A. Belonging needs