CATA Exam Newest 2025 Complete 900 Questions And Correct Detailed Answers (Verified
Answers) |Already Graded A+
Students have to change buildings between classes,
which often involves walks of 5 minutes or more.
Walking from one building to another is
a waste
non-value-added time
value-added time. - (answer)non-value-added time
Such walks are not waste, as they are required given
the current lay-out of the campus. However (unless
the students take great joy in the walk), they do not
add value to the customer; they are thus non-value
add time.
Non-Value Added - (answer)a processing step that
does not enhance the product but must be done
value added time - (answer)the time in which useful
work is actually being done on the unit
,CATA Exam Newest 2025 Complete 900 Questions And Correct Detailed Answers (Verified
Answers) |Already Graded A+
What are the two pillars of the Toyota Production
System?
a Just-in-time and waste reduction
b Waste reduction and built-in quality
c Built-in quality and just-in-time
d Process improvement and waste reduction -
(answer)c Built-in quality and just-in-time Correct
Built-in Quality - (answer)Built-In Quality practices
ensure that each Solution element, at every
increment, meets appropriate quality standards
throughout development.
just in time - (answer)a logistics process in which
goods arrive when needed for production, use, or
sale rather than sitting in storage
,CATA Exam Newest 2025 Complete 900 Questions And Correct Detailed Answers (Verified
Answers) |Already Graded A+
Which of the following does not belong to the seven
sources of waste?
a Rework
b Overtime
c Transportation
d Inventory - (answer)b Overtime
Seven Sources of Waste - (answer)Inventory
Overproduction
Waiting time
Unnecessary transporting
Processing waste
Inefficient work methods
Product defects
, CATA Exam Newest 2025 Complete 900 Questions And Correct Detailed Answers (Verified
Answers) |Already Graded A+
What is the roof in the "house-shaped"
representation of the Toyota Production System?
a Just-in-time
b Waste reduction
c Built-in quality
d Process improvement - (answer)b Waste reduction
The roof is the reduction of waste by better matching
supply with demand. This includes the waste of time
of the flow units and the waste of resources.
What is the relationship between the number of
kanban cards in a process and the inventory level?
a There is no relationship between the two.
Answers) |Already Graded A+
Students have to change buildings between classes,
which often involves walks of 5 minutes or more.
Walking from one building to another is
a waste
non-value-added time
value-added time. - (answer)non-value-added time
Such walks are not waste, as they are required given
the current lay-out of the campus. However (unless
the students take great joy in the walk), they do not
add value to the customer; they are thus non-value
add time.
Non-Value Added - (answer)a processing step that
does not enhance the product but must be done
value added time - (answer)the time in which useful
work is actually being done on the unit
,CATA Exam Newest 2025 Complete 900 Questions And Correct Detailed Answers (Verified
Answers) |Already Graded A+
What are the two pillars of the Toyota Production
System?
a Just-in-time and waste reduction
b Waste reduction and built-in quality
c Built-in quality and just-in-time
d Process improvement and waste reduction -
(answer)c Built-in quality and just-in-time Correct
Built-in Quality - (answer)Built-In Quality practices
ensure that each Solution element, at every
increment, meets appropriate quality standards
throughout development.
just in time - (answer)a logistics process in which
goods arrive when needed for production, use, or
sale rather than sitting in storage
,CATA Exam Newest 2025 Complete 900 Questions And Correct Detailed Answers (Verified
Answers) |Already Graded A+
Which of the following does not belong to the seven
sources of waste?
a Rework
b Overtime
c Transportation
d Inventory - (answer)b Overtime
Seven Sources of Waste - (answer)Inventory
Overproduction
Waiting time
Unnecessary transporting
Processing waste
Inefficient work methods
Product defects
, CATA Exam Newest 2025 Complete 900 Questions And Correct Detailed Answers (Verified
Answers) |Already Graded A+
What is the roof in the "house-shaped"
representation of the Toyota Production System?
a Just-in-time
b Waste reduction
c Built-in quality
d Process improvement - (answer)b Waste reduction
The roof is the reduction of waste by better matching
supply with demand. This includes the waste of time
of the flow units and the waste of resources.
What is the relationship between the number of
kanban cards in a process and the inventory level?
a There is no relationship between the two.