ARE 5.0 MOCK EXAM – PCM 2025
QUESTIONS AND ANSWERS
An architecture firm is facing a deadline on a large library project and decides to hire a
freelance computer-aided design (CAD) drafter who works from home to assist the firm
in completing the construction documents on time. According to the National Council
of Architectural Registration Boards (NCARB) RULES OF CONDUCT, what must the
architect of record do to sign and seal the final drawings?
A. The architect must redline the drawings and have the drafter make the appropriate
corrections
B. The architect must review and correct the work after it is prepared by the drafter and
incorporate it into the construction documents
C. The architect must thoroughly examine the drawings prepared by the drafter and
incorporate the work into the construction documents. The firm must also retain
documentation of communications with the drafter throughout the drafter's involvement
with the project and must keep records of the arch - ....ANSWER ...-C
Which types of business organization limit an individual's liability to the amount that an
individual has invested in the company? Choose 3.
....FOR STUDY PURPOSES...©️2025 ALL RIGHTS RESERVED... 1
,A. partnership
B. corporation
C. joint venture
D. limited liability company
E. limited liability partnership
F. disadvantaged business enterprise - ....ANSWER ...-B D E
Which of the following are required to prove negligence? Choose 4.
A. agency
B. breach
C. cause
D. commission
E. damage
F. duty - ....ANSWER ...-B C E F
An architect writes a specification for floor tile for a public restroom, which states that
the tile is to be "American Tile Company 12 x 12 porcelain floor tile, Pattern 463 Oceania,
Color 42 Sandstorm or approved equal". The contractor contacts a local tile supplier and
discovers that this product has a 12-weel lead time, but it will be necessary to have the
tile on site earlier to stay within the project schedule. If the contractor wishes to propose
a different tile, when must that request to the architect be submitted?
....FOR STUDY PURPOSES...©️2025 ALL RIGHTS RESERVED... 2
,A. during preparation of submittals
B. prior to submitting a bid
C. after the contract is awarded and an agreement with the tiling subcontractor is signed
D. during the project kick-off meeting - ....ANSWER ...-B
According to the national Council of Architectural Registration Boards (NCARB)
RULES OF CONDUCT, an architect's license or registration could be revoked if :
A. in talking with a potential client, the architect fails to disclose ownership of stock in
the client's chief competitor and that personal financial interest may influence the
architect's judgement
B. in a television interview about a controversial casino project, the architect discloses
that he or she is employed by the resort developer
C. the architect pays for overnight accommodation and a dinner for a potential client so
that the client may visit the architect's firm for a second interview about a large project
D. the architect takes out a half-page advertisement in a local newspaper stating the
firm's credentials and why the firm should be considered for a large development project
in the city - ....ANSWER ...-A
What must architect do to protect their interest in the copyright on the instruments of
service produced for a project and the design of a building?
A. Register the drawings and photographs of the completed building with the U.S.
Copyright Office
....FOR STUDY PURPOSES...©️2025 ALL RIGHTS RESERVED... 3
, B. File a copy of the instruments of service in the Library of Congress
C. Put the copyright symbol and the date on the drawings
D. Neither option A, B, or C are required to project the architect's copyright -
....ANSWER ...-D
"Vinyl composition tile shall be maintained at a minimum of 65 degrees F for 48 hours
prior to installation, during installation, and for 48 hours after completion". In what part
of the project specifications does the contractor find these instructions?
A. Part I, General
B. Part II, Products
C. Part III, Execution
D. Division 01, General Requirements - ....ANSWER ...-C
Which of the following is the best way to modify a standard American Institute of
Architects (AIA) document?
A. Retype the document, incorporating all of the changes
B. Attach supplementary conditions or amendments
C. Strike out portions of the contract by hand or insert handwritten additions.
D. Have an attorney draft a new contract using portions of the language in the AIA
documents applicable to the project - ....ANSWER ...-B
"Claims - made" professional liability insurance policies :
....FOR STUDY PURPOSES...©️2025 ALL RIGHTS RESERVED... 4
QUESTIONS AND ANSWERS
An architecture firm is facing a deadline on a large library project and decides to hire a
freelance computer-aided design (CAD) drafter who works from home to assist the firm
in completing the construction documents on time. According to the National Council
of Architectural Registration Boards (NCARB) RULES OF CONDUCT, what must the
architect of record do to sign and seal the final drawings?
A. The architect must redline the drawings and have the drafter make the appropriate
corrections
B. The architect must review and correct the work after it is prepared by the drafter and
incorporate it into the construction documents
C. The architect must thoroughly examine the drawings prepared by the drafter and
incorporate the work into the construction documents. The firm must also retain
documentation of communications with the drafter throughout the drafter's involvement
with the project and must keep records of the arch - ....ANSWER ...-C
Which types of business organization limit an individual's liability to the amount that an
individual has invested in the company? Choose 3.
....FOR STUDY PURPOSES...©️2025 ALL RIGHTS RESERVED... 1
,A. partnership
B. corporation
C. joint venture
D. limited liability company
E. limited liability partnership
F. disadvantaged business enterprise - ....ANSWER ...-B D E
Which of the following are required to prove negligence? Choose 4.
A. agency
B. breach
C. cause
D. commission
E. damage
F. duty - ....ANSWER ...-B C E F
An architect writes a specification for floor tile for a public restroom, which states that
the tile is to be "American Tile Company 12 x 12 porcelain floor tile, Pattern 463 Oceania,
Color 42 Sandstorm or approved equal". The contractor contacts a local tile supplier and
discovers that this product has a 12-weel lead time, but it will be necessary to have the
tile on site earlier to stay within the project schedule. If the contractor wishes to propose
a different tile, when must that request to the architect be submitted?
....FOR STUDY PURPOSES...©️2025 ALL RIGHTS RESERVED... 2
,A. during preparation of submittals
B. prior to submitting a bid
C. after the contract is awarded and an agreement with the tiling subcontractor is signed
D. during the project kick-off meeting - ....ANSWER ...-B
According to the national Council of Architectural Registration Boards (NCARB)
RULES OF CONDUCT, an architect's license or registration could be revoked if :
A. in talking with a potential client, the architect fails to disclose ownership of stock in
the client's chief competitor and that personal financial interest may influence the
architect's judgement
B. in a television interview about a controversial casino project, the architect discloses
that he or she is employed by the resort developer
C. the architect pays for overnight accommodation and a dinner for a potential client so
that the client may visit the architect's firm for a second interview about a large project
D. the architect takes out a half-page advertisement in a local newspaper stating the
firm's credentials and why the firm should be considered for a large development project
in the city - ....ANSWER ...-A
What must architect do to protect their interest in the copyright on the instruments of
service produced for a project and the design of a building?
A. Register the drawings and photographs of the completed building with the U.S.
Copyright Office
....FOR STUDY PURPOSES...©️2025 ALL RIGHTS RESERVED... 3
, B. File a copy of the instruments of service in the Library of Congress
C. Put the copyright symbol and the date on the drawings
D. Neither option A, B, or C are required to project the architect's copyright -
....ANSWER ...-D
"Vinyl composition tile shall be maintained at a minimum of 65 degrees F for 48 hours
prior to installation, during installation, and for 48 hours after completion". In what part
of the project specifications does the contractor find these instructions?
A. Part I, General
B. Part II, Products
C. Part III, Execution
D. Division 01, General Requirements - ....ANSWER ...-C
Which of the following is the best way to modify a standard American Institute of
Architects (AIA) document?
A. Retype the document, incorporating all of the changes
B. Attach supplementary conditions or amendments
C. Strike out portions of the contract by hand or insert handwritten additions.
D. Have an attorney draft a new contract using portions of the language in the AIA
documents applicable to the project - ....ANSWER ...-B
"Claims - made" professional liability insurance policies :