___ is a pre-installation activity. Ans✓✓✓ Planning
___ should always be formally documented, agreed to, and signed by all
major parties, as well as the appointed member of the AV systems
integration firm. Ans✓✓✓ Changes
A primary reason for attending construction meetings is to? Ans✓✓✓
Identify changes to the original design that will affect the AV
installation.
A scope statement should include? Ans✓✓✓ Both in-scope and out-of-
scope items.
After which of the following activities is an AV project completed?
Ans✓✓✓ System closeout activities are completed.
AV Installation Ans✓✓✓ The successful installation of an AV system.
AV Verification Ans✓✓✓ Verifying that the AV installation meets the
documented specifications.
Before developing a project plan, it is important to? Ans✓✓✓ Have a
clear understanding of the scope of work.
, Change Order Ans✓✓✓ This document is used to document agreed-
upon changes to the project specifications or contract as the project
progresses.
Construction Change Directive (CCD) Ans✓✓✓ This form, also known
as a field order, is usually issued for a time-critical condition or event
that needs an immediate change.
Cost Ans✓✓✓ Estimates human and material resources
Deliverable Scope and Project Scope Ans✓✓✓ Two distinct
components of a scope statement.
Deliverable Scope Ans✓✓✓ The features and functions that
characterize a product, process, or service to be delivered. It states what
will be delivered.
During the planning stages, you will need to have a clear understanding
of the client's ___ and ___ for the AV installation. Ans✓✓✓ objectives,
purpose
Effectively communicating with all the people involved in the project is
essential for ___. Ans✓✓✓ success