The 1970s law that set into place the regulation of stormwater
is - correct answer- The clean water act
Requirements for managing stormwater activity on a
construction site are outlined in the following regulation -
correct answer- NPDES
Which of the following is never an allowable stormwater
discharge from a construction site - correct answer- Discharge
from contaminated ground water
The notice of termination can be filed when - correct answer- All
construction activity, inside and outside of the building, is
complete and permanent stabilization has been verified as
adequate to meet permit requirements
, 2 | Page
Relative to stormwater permitting all of the following must occur
before construction starts except - correct answer- Submit the
notice of termination (NOT)
The stormwater notice of intent (NOI) must be submitted -
correct answer- After the SWPPP is prepared and before
starting construction
Potential pollutant sources stored on a construction site may
include - correct answer- 1. Petroleum storage tanks
2. Soil sediments
3. Masonary material
4. ALL OF THE ABOVE
The SWPPP inflammation sequence may be modified - correct
answer- After consulting with the project SWPPP Designer
(CEC) and, if required, the project owner and receiving written
approval
A SWPPP site map will show all of the following except -
correct answer- Notices of violation
DVP SWPPP EXAM 2025 UPDATED
ACTUAL EXAM WITH CORRECT
SOLUTIONS.
The 1970s law that set into place the regulation of stormwater
is - correct answer- The clean water act
Requirements for managing stormwater activity on a
construction site are outlined in the following regulation -
correct answer- NPDES
Which of the following is never an allowable stormwater
discharge from a construction site - correct answer- Discharge
from contaminated ground water
The notice of termination can be filed when - correct answer- All
construction activity, inside and outside of the building, is
complete and permanent stabilization has been verified as
adequate to meet permit requirements
, 2 | Page
Relative to stormwater permitting all of the following must occur
before construction starts except - correct answer- Submit the
notice of termination (NOT)
The stormwater notice of intent (NOI) must be submitted -
correct answer- After the SWPPP is prepared and before
starting construction
Potential pollutant sources stored on a construction site may
include - correct answer- 1. Petroleum storage tanks
2. Soil sediments
3. Masonary material
4. ALL OF THE ABOVE
The SWPPP inflammation sequence may be modified - correct
answer- After consulting with the project SWPPP Designer
(CEC) and, if required, the project owner and receiving written
approval
A SWPPP site map will show all of the following except -
correct answer- Notices of violation