ARE 5.0 NCARB UPDATED ACTUAL Exam Questions and CORRECT Answers Public - CORRECT ANSWER - Which of the following methods of bidding is required on most projects for which government funds are to be used? A. Direct B. Negotiated C. Invited D. Public Fast track - CORRECT ANSWER - Which of the following project delivery methods always requires preparation of several individual bid-document packages?

Content preview

ARE 5.0 NCARB UPDATED ACTUAL
Exam Questions and CORRECT Answers
Public - CORRECT ANSWER - Which of the following methods of bidding is required on
most projects for which government funds are to be used?


A. Direct
B. Negotiated
C. Invited
D. Public


Fast track - CORRECT ANSWER - Which of the following project delivery methods
always requires preparation of several individual bid-document packages?


A. Design-Bid-Build
B. Fast Track
C. Design Build
D. Turnkey


Specifications - CORRECT ANSWER - diagram on paper



recommend qualified contractors - CORRECT ANSWER - In developing a list of bidders
for a private project, the architect's role is to


A. select the contractor
B. recommend qualified contractors
C. rank the contractors in order of preference
D. discourage owner-recommended contractors

,surety - CORRECT ANSWER - A contractor's ability to obtain a performance bond for a
specific contract is determined by the


A. owner
B. architect
C. contractor
D. surety


Financial statment - CORRECT ANSWER - AIA Document A305, Contractor's
Qualification Statement, requires which of the following supplemental documents to be provided
by the applicant?


A. financial statement
B. list of subcontractors
C. list of proposed consultants
D. list of proposed material suppliers


Has the right to waive irregularities and accept the bid - CORRECT ANSWER - After
considering all the bids, the owner favors a bid with irregularities. According to AIA Document
A701, Instructions to Bidders, the owner has which of the following rights/responsibilities
regarding an irregular bid?


A. Has the right to waive irregularities and accept the Bid
B. Has the right to extend the bidding period for corrections
C. Must informally request corrections from the bidder
D. Must only consider bids without irregularities


multiple prime contracts - CORRECT ANSWER - A local bank has a budget of
$30,000,000 to construct a new main office. The bank wants to use contractors who are
customers of the bank; however, none of the bank's contractor customers can bond the entire

, amount of the contract. Which of the following delivery methods would be best suited to meeting
the bank's contractor selection goal?


A. Design-Build
B. Fast-Track
C. Multiple-Prime Contracts
D. Additive change Orders


notification of future addenda - CORRECT ANSWER - Which of the following is an
appropriate item for the prebid conference?


A. Occupancy-permit procedures
B. Notification of future addenda
C. Pre-commissioning procedures
D. Status of Change Orders


The contractor is required to replace the lighting fixtures wiht the fixtures specified without
remibursement - CORRECT ANSWER - A contractor under a fixed-price construction
contract has allowed the electrical subcontractor to install lighting fixtures other than those stated
in the contract documents. The electrical subcontractor and the contractor both believe the
substituted fixtures to be of equal value. The construction is substantially completed and the
architect rejects these fixtures. According to AIA Document A201, General Conditions, which of
the following actions must be taken regarding the lighting fixtures?


A. The architect must accept the lighting fixtures as installed without a cost credit to the owner.
B. The architect must accept the lighting fixtures as installed but with a cost credit to the owner.
C. The contractor is required to replace the lighting fixtures with the fixtures specified without
reimbursement.
D. The contractor is required to replace the lighting fixtures specified but is entitled to
reimbursement for labor costs for the replacement.

Document information

Uploaded on
June 24, 2025
Number of pages
16
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$12.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
MGRADES
4.0
(235)
Sold
1538
Followers
108
Items
110360
Last sold
1 day ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions