Questions and CORRECT Answers
All of the following are deliverables of the Define phase EXCEPT _____.
(A.) Project Y in Y=f(x)
(B.) Expected benefits
(C.) Problem and goal statements
(D.) List of Solutions - CORRECT ANSWER - (D.) List of Solutions
(TRUE or FALSE) Cost of Poor Quality (COPQ) reduction targeted by the project should be
quantified during the Define phase. - CORRECT ANSWER - TRUE
The Black Belt should confirm the focus and scope of the project with the _____.
(A.) Black Belt's Supervisor
(B.) Project Team
(C.) Master Black Belt
(D.) Project Champion - CORRECT ANSWER - (D.) Project Champion
Who selects the project ?
(A.) Project Team
(B.) Black Belt
(C.) Project Champion
(D.) Master Black Belt - CORRECT ANSWER - (C.) Project Champion
Project plans should include all of the following EXCEPT _____.
, (A.) Goals & Objectives
(B.) Timing & Milestones
(C.) Deliverables or Outputs
(D.) Steps & Tasks - CORRECT ANSWER - (A.) Goals & Objectives
Project team members are _____.
(A.) Interested employees who volunteer
(B.) Selected by the Champion and assigned by management
(C.) All stakeholders and process owners
(D.) Employees selected and assigned by their department heads - CORRECT ANSWER -
(B.) Selected by the Champion and assigned by management
In the Define phase, the ____ is defined.
(A.) X
(B.) Y and Xs
(C.) Y
(D.) Y=f(x) - CORRECT ANSWER - (C.) Y
(TRUE or FALSE) Alignment means project success supports achievement of the organization's
annual and strategic goals - CORRECT ANSWER - TRUE
(TRUE or FALSE) Project Charter is the key deliverable in the Define phase - CORRECT
ANSWER - TRUE
The main focus of the Measure phase is to measure the _____.
(A.) Y in Y=F(x)